Partnership Project Schedule
     
  June 10, 2003 Advisory Group Meeting
  June 10 - July 2, 2003 Internal & External Interviews
  July 1 - July 11, 2003 Internal & External Focus Group Meetings
  July 25, 2003 Advisory Group Meeting
  July 28 - August 17,2003 Citizen & Stakeholder Survey
  September 23, 2003 Advisory Group Meeting
  November 2003 Estimated Completion (Phase I)
  December 2003 - July 2004 Implementation (Phase II)
     