TopekaandLawrenceMetroLogog

Daily Traffic Information

for

Friday, March 27, 2015

  

 (NEW - REVISED)

 


 

SHORT TERM

 

Short term project closures listed below typically take place during daylight hours. Project completion dates typically range from 1 to 30 days. All closures and scheduled work are weather permitting and subject to change.

 

 

SHAWNEE COUNTY 

 

 

 No short-term project closures at this time.

 

 

DOUGLAS COUNTY 

 

 

 No short-term project closures at this time.

 


 

LONG TERM

 

Long term project closures listed below typically take place 24 hours a day, 7 days a week. Project completion dates typically range from 31 days up to a year. All closures and scheduled work are weather permitting and subject to change.

 

SHAWNEE COUNTY

 

 

No long-term project closures at this time.

 

DOUGLAS COUNTY

  

K-10 & Bob Billings Parkway Interchange Project
Overall project work is scheduled to be completed in early November 2015

N 1500 Road Closure at K-10

24/7 ROADWAY CLOSURE ACCESS: N 1500 Road on west side of K-10 intersection and the northbound K-10 left turn lane to N 1500 Road will be CLOSED, 24/7 round the clock, for reconstruction work for the new K-10 & Bob Billings Parkway interchange beginning after morning rush hour on Monday, October 27 through late summer 2015. There will be no access for northbound K-10 traffic to westbound N 1500 Road or for eastbound N 1500 Road traffic to K-10 (on west side of intersection). No marked detours will be provided. There will be a 55 mph posted speed limit on K-10 through the project work zone throughout the project duration. Drivers should expect delays during peak commute times and must use alternate routes throughout the duration of the project. Project work is scheduled to be completed in late summer 2015. (NEW 10-24-14) 

K-10

WEEKDAY WORK: Beginning on Monday, July 28, project work will begin to construct a new diamond interchange at K-10 and Bob Billings Parkway. Most work will take place off the highway itself, so there will be little to no traffic impacts in the early phases of construction. Project work is scheduled to be completed in early November 2015. (NEW 7-25-14) 

K-10 South Lawrence Trafficway > > #K10SLT 
Overall project work is scheduled to be completed in Fall 2016

On Tuesday, November 12, 2013, a three-year construction project began to complete the six-mile four-lane K-10 South Lawrence Trafficway freeway. The project will move existing K-10 onto a new alignment that will begin at the south junction of the U.S. 59 and K-10 interchange and reconnect with existing K-10 in east Lawrence (Douglas County). Construction work on the project will be completed in phases. Each phase includes specific work and advance notification will be sent under separate cover for each phase of construction, including planned traffic impacts. An aerial map of the new K-10 South Lawrence Trafficway, including construction phasing and traffic impacts, can be found online at: http://www.ksdot.org/topekaMetro/projectstudytest.asp.

K-10 from E1650 Road to E1900 Road

EXPECT MINOR DELAYS! 24/7 LANE CLOSURES: Eastbound and westbound K-10 LEFT LANES from E1650 Road to E1900 Road will be CLOSED, 24/7 round the clock, beginning at 8:00 a.m. on Monday March 16. Noria Road/E1750 Road to the north of K-10 will also be FULLY CLOSED PERMANENTLY to all traffic at the same time. When the interchange is completed later this year, Noria Road traffic will travel over K-10 via a new bridge. The lane closures are needed so the contractor can construct the new K-10 and 23rd Street interchange which is part of the ongoing K-10 South Lawrence Trafficway Project (East Leg). E1900 Road and County Road 442 will remain open to the traveling public. There will be no marked detour for the Noria Road/E1750 Road closure, but the public will be able to access Noria Road from East Hills Road to the west or E1900 Road to the east. Project work is scheduled to be completed in late December 2015. (NEW 3-11-15)

Haskell Avenue

TRAFFIC SHIFT: Northbound and southbound Haskell Avenue from 27th Street to 31st Street will be REOPENED to traffic with the following traffic restrictions in Lawrence (Douglas County) on Monday, August 4 at 9:00 a.m., weather permitting. Southbound traffic on Relocated Haskell Avenue must turn right (west) onto 29th Street, then left (south) onto existing Haskell Avenue. Northbound traffic on existing Haskell Avenue must turn right (east) onto 29th Street, then left (north) onto relocated Haskell Avenue. HiPer Technology’s existing business entrance off of existing Haskell Avenue will be closed, and the new business entrance for HiPer Technology will be on the east end of 29th Street. (NEW 7-29-14)

Louisiana Street & 31st Street

24/7 ROADWAY CLOSURE: Northbound and southbound Louisiana Street south of Broken Arrow Park and eastbound and westbound 31st Street west of Wakarusa Fire Station will be CLOSED to all traffic in Lawrence (Douglas County) on Monday, August 4 at NOON 12:00 p.m. through Spring 2015, weather permitting. This will extend the current Louisiana Street closure from Steve’s Place business entrance to Broken Arrow Park entrance (including the intersection of 31st Street and Louisiana Street).  The existing 31st Street closure will extend east to the Wakarusa Fire Station entrance meaning 31st Street will now be closed from Ousdahl Road to the Wakarusa Fire Station entrance. Project work is scheduled to be completed in Spring 2015. (NEW 7-29-14)

24/7 ROADWAY CLOSURE: Northbound and southbound Louisiana Street from N1250 Road south to the south side of the Wakarusa Bridge will be CLOSED to all traffic in Lawrence (Douglas County) on Monday morning, August 11 through Spring 2015. Project work is scheduled to be completed in Summer 2015. (NEW 8-11-14)

O’Connell Road (E1600 Road) & 31st Street (N1300 Road) Intersection

24/7 INTERSECTION CLOSURE: O’Connell Road (E1600 Road) & 31st Street (N1300 Road) Intersection will be CLOSED, 24/7 round the clock, for roundabout construction work beginning on Tuesday, September 2 and will reopen in spring 2015, weather permitting. Project work is scheduled to be completed in Spring 2015. (NEW 8-28-14)

31st Street

24/7 FULL ROADWAY CLOSURES: Eastbound and westbound 31st Street from E1700 Road to E1750 Road in Lawrence (Douglas County) will be CLOSED, 24/7 round the clock, for box culvert construction work beginning on Monday, December 9 at 7:00 a.m., weather permitting, through Spring 2015. (Rev. 12-30-13)

24/7 FULL ROADWAY CLOSURES: Eastbound and westbound 31st Street from Louisiana Street to approximately .25-miles west and Louisiana Street just south of 31st Street in Lawrence (Douglas County) will be CLOSED, 24/7 round the clock, for construction work beginning on Tuesday, June 3, 2014 at 7:00 a.m., through summer 2015, weather permitting. No marked detours will be provided. Project work is scheduled to be completed in Summer 2015. (NEW 5-29-14)

N1500 Road

24/7 FULL ROADWAY CLOSURES: Eastbound and westbound N1500 Road from E900 Road to K-10 will be CLOSED, 24/7 round the clock, for construction work beginning on Monday, August 18 through Spring 2015. Project work is scheduled to be completed in Spring 2015. (NEW 8-20-14)

E1750 Road

24/7 FULL ROADWAY CLOSURES: Northbound and southbound E1750 Road from past the intersection of N1360 Road/25th Street to N1250 Rd/35th Street will be CLOSED, 24/7 round the clock, for bridge embankment work beginning on Monday morning, August 11 through Spring 2015. Project work is scheduled to be completed in Summer 2015. (NEW 8-11-14)