 |
Topeka/Lawrence Metro Area
Lane Closure Info
Thursday, February 9, 2012
(NEW / REVISED)
WEATHER
PERMITTING |
SHORT TERM
Short term project closures listed below typically take place during daylight hours. Project completion dates typically range from
1 to 30 days, weather permitting.
No projects at this time.
No projects at this time.
LONG TERM
Long term project closures listed below typically take place 24 hours a day, 7 days a week. Project completion dates typically range from
31 days up to a year, weather permitting.
DOUGLAS COUNTY
US-59
In January 2009, construction began on the US-59 highway realignment project. The US-59 realignment project will occur in two phases in Douglas County. Phase I, which began in January 2009, includes grading (earthwork) and construction of bridges. Phase II includes the surfacing/pavement work for the new 11.1-mile stretch of US-59 roadway. Traffic impacts during Phase I will be minimal as construction is taking place adjacent to the road. Specific traffic impacts will be reported as needed. Project work is scheduled to be completed in late 2012. (New 7-6-09)
200N Road at US-59
Beginning at noon on Wednesday, July 29, 200N Road will close at US-59 for frontage road construction work. 200N Rd will be tied into a new frontage road that runs parallel to the new US-59 (see above). Project work is scheduled to be completed in late 2012. (New 7-28-09)
SHAWNEE COUNTY
No projects at this time.
|