I-235 Green Project


  • Traffic on I-235
    A glimpe at the recent past: Southbound I-235 traffic is no longer on these lanes and northbound lanes are fully open.
  • Removal of old SB I-235
    Dirt work and concrete pavement placement is now a thing of the past. All three lanes of SB I-235 are open (plus the SB I-235 ramps at Broadway).
  • L. Ark River bridge pour
    A bridge pour on a new bridge over the Little Arkansas River was successfully completed in spite of distant lightning. Traffic is now using the new bridge.
  • Removal of Seneca bridge over 235
    The Seneca Street bridge over I-235 was removed and will not be replaced. Businesses and residents now have access from N. Meridian Avenue.
 
 

 

About the Green Project

Work on the I-235 Green Project began on March 11, 2019 and was completed November 24, 2021.

The Green Project is the first phase of the Wichita North Junction rebuild. It sets up I-235 to function with the future phases that improve the North Junction. Highlights include:

 Replacement of aging pavement

Auxiliary lanes on I-235

 Permanent removal of the Seneca St. bridge

A rebuild of the Broadway Interchange

Replacement of the bridges over the Little Arkansas River

Replacement of the bridges over Broadway

Current Traffic Impacts

 

 

Coming Soon 

• All lanes of traffic and ramps are open.

More Information

For a fact sheet on the Green Project, the first phase of the North Junction fix, click here.

For a fact sheet on the three phases of projects for the North Junction reconstruction, click here.

More information about KDOT in the Wichita Metro is here.