KCMetroLogo

Daily Traffic Information

 

for

 

Tuesday, August 30, 2016

 


 

SHORT-TERM

 

Short-term project closures listed below typically take place during daylight hours. Project completion dates typically range from 1 to 30 days. All closures and scheduled work are weather permitting and subject to change.

 

 

JOHNSON COUNTY 

 Johnson County Gateway  >   #jocogateway    

I-35 & I-435 Interchange  

WEEKDAY SLOW MOVING RAMP CLOSURE: Northbound/westbound I-435 at K-10 to have SLOWDOWNS via a rolling roadblock for blasting work to remove rock at 2 p.m. on Tuesday-Thursday, August 30-September 1. Project work is scheduled to be completed on Thursday, September 1. (NEW 8-29-16) 

WEEKDAY OVERNIGHT RAMP TURN LANE CLOSURE: Northbound I-35 FAR MOST RIGHT TURN LANE on eastbound 95th Street exit ramp CLOSED for median island work at 9 p.m. on Monday, August 29 and reopening at 5 a.m. on Tuesday, August 30. Traffic can still access northbound I-35 from the center/through lane. Project work is scheduled to be completed on Tuesday, August 30. (NEW 8-25-16) 

WEEKDAY OVERNIGHT RAMP CLOSURES: Eastbound I-435 to southbound I-35 ramp CLOSED overnight for traffic switch work onto new ramp pavement beginning at 10 p.m. on Monday, August 29 and will reopen at 5 a.m. on Tuesday, August 30, weather permitting. Traffic will detour via northbound I-35 to 95th Street exit, via left turns through new Diverging Diamond Interchange to access southbound I-35.Project work is scheduled to be completed on Tuesday, August 30. (NEW 8-25-16)  

95th Street

WEEKDAY OVERNIGHT LANE CLOSURE: Westbound 95th Street RIGHT LANE over Lenexa Drive CLOSED for epoxy application work beginning at 9 p.m. on Tuesday, August 30 and reopening at 5 a.m. on Wednesday, August 31. Traffic can still access northbound I-35 from the center/through lane. Project work is scheduled to be completed on Wednesday, August 31. (NEW 8-25-16) 

WEEKDAY OVERNIGHT LANE CLOSURE: Eastbound and westbound 95th Street LEFT LANES over Lenexa Drive CLOSED for epoxy application work beginning at 9 p.m. on Monday, August 29 and reopening at 5 a.m. on Tuesday, August 30. Project work is scheduled to be completed on Tuesday, August 30. (NEW 8-25-16) 

WEEKDAY OVERNIGHT LANE CLOSURE: Eastbound and westbound 95th Street LEFT TURN LANES at Monrovia Street CLOSED for median island work beginning at 9 p.m. on Tuesday, August 30 and reopening at 5 a.m. on Wednesday, August 31. Project work is scheduled to be completed on Wednesday, August 31. (NEW 8-29-16) 

Pflumm Road at I-435

WEEKDAY OVERNIGHT FULL ROAD CLOSURES: Northbound and southbound Pflumm Road under the I-435 bridges FULLY CLOSED for the setting of I-435 bridge girders overnight beginning at 8 p.m. on Monday, August 29 and at 10 p.m. on Tuesday, August 30 and reopening at 5 a.m. on Tuesday-Wednesday, August 30-31, respectively, weather permitting. Advance message boards are in place to alert drivers the roadway closure. A marked detour will be provided via College Boulevard to Quivira Road to 103rd Street. Project work is scheduled to be completed on Wednesday, August 31. (NEW 8-25-16)


I-35 from Southwest Boulevard to 95th Street Resurfacing Project

WEEKDAY/WEEKEND DAY OVERNIGHT LANE & RAMP CLOSURES:  The following I-35 lane and ramps CLOSED for resurfacing work. (NEW 8-29-16)  

No short-term project closures at this time.

I-35 from 151st Street to Santa Fe Street Reconstruction Project

24/7 LANE CLOSURE: Southbound I-35 LEFT LANE/SHOULDER from 127th Street to Santa Fe Street Bridge CLOSED, 24/7 round the clock, for median crossover work beginning at 9 a.m. on Wednesday, August 17 thru early September 2016. Project work is scheduled to be completed in early September 2016. (NEW 8-16-16) 

TRAFFIC SWITCH WORK UNDERWAY THIS WEEK! Northbound and southbound I-35 from 151st Street to Santa Fe Street/135th Street will have the following traffic shirt impacts taking place this week, Monday-Friday, August 29-September 1, weather permitting. Project work is scheduled to be completed on Friday, September 1. (NEW 8-29-16)

Here’s what this means for drivers as follows: 

  • > > > SPECIAL NOTE > > >Old US-56 to northbound I-35 entrance ramp will remain CLOSED. Due to delays on the bridge repairs, it will reopen at a later date.

Monday, August 29; 9 AM-3 PM > Southbound I-35 RIGHT LANE from Santa Fe Street to 151st Street/U.S. 169 CLOSED for sign work.

Monday, August 29; 9 AM-3 PM, > Northbound I-35 LEFT LANE from 151st Street/U.S. 169 to Old US-56 CLOSED for temporary barrier removal.

Wednesday, August 31, 12:01 AM-6 PM > Southbound I-35 RIGHT TWO LANES from 127th Street to 151st Street/U.S. 169 CLOSED for permanent pavement markings

Wednesday, August 31, 6 PM > Open southbound I-35 to its original traffic configuration.

Thursday, September 1, 7 AM > Open Santa Fe Street to southbound I-35 entrance ramp.

Thursday, September 1, 9 AM-3 PM > Southbound I-35 RIGHT LANE at Santa Fe Street CLOSED for temporary barrier removal and temporary pavement removal

Friday, September 2, 3 PM > Open northbound I-35 to its original configuration.

K-7/Parker Street

WEEKDAY LANE CLOSURES: Northbound K-7/Parker Street at eastbound Dennis Avenue REDUCED TO ONE OPEN LANE for construction of a new right turn lane beginning on Thursday, August 25 through late September 2016, between 8:30 a.m. and 4 p.m. daily. Project work is scheduled to be completed in late September 2016. (NEW 8-24-16) 

WEEKDAY LANE CLOSURE: Westbound Old U.S. 56 at northbound K-7/Parker Street REDUCED TO ONE OPEN LANE for construction of a new right turn lane beginning on Friday, August 26 through late September 2016, between 8:30 a.m. and 4 p.m. daily. Project work is scheduled to be completed in late September 2016(NEW 8-24-16) 

 

 

LEAVENWORTH COUNTY

  

 

No short-term project closures at this time.

 

 

 

WYANDOTTE COUNTY

 

 

I-70

UPCOMING WEEKDAY RAMP CLOSURE: Westbound I-70 to Fairfax Avenue ramp CLOSED for routine bridge maintenance work on Wednesday, August 31 between 9 a.m. and 3 p.m. No marked detour will be provided. Project work will be completed on Wednesday, August 30. (NEW 8-29-16)

WEEKDAY LANE CLOSURE: Westbound I-70 LEFT LANE from Riverview Avenue to K-7 CLOSED for setting of temporary barrier on Tuesday, August 30 between 9 a.m. and 3 p.m. Project work will be completed on Wednesday, August 30. (NEW 8-29-16)

U.S. 69/18th Street Expressway

WEEKDAY OVERNIGHT LANE & RAMP CLOSURES: Northbound and southbound U.S. 69/18th Street Expressway from Kansas Avenue to Merriam Lane reduced to ONE OPEN LANE for overlay work overnight between 6 p.m. and 6 a.m. on Wednesday-Wednesday, August 3-31, weather permitting. Varying ramps at U.S. 69/18th Street and Kansas Avenue, Ruby Street, Steele Road and Merriam Lane CLOSED for overlay work overnight between 6:30 p.m. and 6 a.m. on Wednesday-Wednesday, August 3-31, weather permitting. Project work is scheduled to be completed on Wednesday, August 31. (NEW 8-2-16)

Merriam Lane Pavement Replacement Project

24/7 LANE CLOSURES: Eastbound Merriam Lane will be CLOSED and detoured onto I-35 exiting at Lamar Avenue/24th Street. Westbound Merriam Lane will have ONE OPEN LANE for approximately 30 days beginning on Tuesday, July 5. Once the eastbound lanes are constructed, the traffic detour will flip, and the westbound traffic will be detoured onto I-35. Project work is scheduled to be completed in Summer 2016. (NEW 7-1-16)

 


  

LONG-TERM

  

Long-term project closures listed below typically take place 24 hours a day, 7 days a week. Project completion dates typically range from 31 days up to a year. All closures and scheduled work are weather permitting and subject to change.

 

 

JOHNSON COUNTY

 

 Johnson County Gateway  >   #jocogateway 

K-10, I-435 & Lackman Road Interchange

LONG-TERM RAMP CLOSURES: Westbound I-435 to Lackman Road exit ramp CLOSED for westbound collector-distributor road construction work, 24/7 round the clock, beginning at 10 p.m. on Friday, July 15 through early October 2016, weather permitting. Westbound I-435 traffic will detour via southbound I-35 to westbound 95th Street to access southbound Lackman Road or via northbound I-435 to eastbound 95th Street to access Lackman Road. Project work is scheduled to be completed in mid-November 2016.  (REV. 8-18-16)

LONG-TERM RAMP CLOSURES: Lackman Road to westbound I-435 entrance ramp CLOSED for westbound collector-distributor road construction work, 24/7 round the clock, beginning at 10 p.m. on Friday, July 15 through early October 2016, weather permitting. Marked detours provided. Southbound Lackman Road traffic will detour via westbound College Boulevard to northbound Renner Boulevard to the K-10 interchange to access westbound I-435. Northbound Lackman Road traffic will detour via westbound 95th Street to the I-435 interchange.  Project work is scheduled to be completed in mid-November 2016.  (REV. 8-18-16)

I-35 & I-435 Interchange Long-Term Loop Ramp Closure 

24/7 LONG-TERM LOOP RAMP CLOSURE: Southbound I-35 to eastbound I-435 loop ramp CLOSED for pavement reconstruction and tie-in work, 24/7 round the clock, beginning at 10 p.m. on Monday, April 11 through late October 2016, weather permitting. SB I-35 to EB I-435 ramp traffic to detour via southbound I-35 to southbound U.S. 69 to eastbound I-435 or via eastbound 119th Street northbound I-35 to eastbound I-435. We recommend that drivers use the detour route via southbound U.S. 69, and NOT the eastbound 119th Street route. The eastbound 119th Street detour route is provided as a backup marked detour route for those drivers who miss the southbound U.S. 69 detour route. Project work is scheduled to be completed in mid-November 2016.  (REV. 8-18-16)

101st Street

LONG-TERM 24/7 LANE CLOSURE: Eastbound 101st Street RIGHT LANE from Lackman Rd to just east of the ramp terminals CLOSED for ramp reconstruction work, 24/7 round the clock, beginning at 6 a.m. on Monday, August 22 through November 2016. Project work is scheduled to be completed in late November 2016. (NEW 8-19-16) 


I-35 at Southwest Boulevard Bridge Repair Project > MODOT PROJECT

24/7 LONG-TERM LANE CLOSURES: Bridge joint replacement will close various lanes of northbound and southbound I-35 on the bridge over Southwest Boulevard near State Line beginning 7 p.m. Monday, Aug. 8 through October. Although work is conducted in separate phases, traffic during peak hours will be maintained with two lanes open in both directions throughout the duration of the project. Motorists should expect delays when traveling in the area, and are urged to seek an alternate route.  All work is weather dependent. Project work is scheduled to be completed in October 2016.  (NEW 8-2-16) 

Southbound I-35 bridge joint replacement includes the following:           

  • Southbound I-35 joint work done in three phases. Traffic will encounter various lane closures for each phase. 
  • One lane of southbound I-35 closing at 7 p.m. Monday, Aug. 8 for traffic control setup.  
  • Southbound I-35 reduced to one lane beginning 9 p.m. Monday, Aug. 8 through 6 a.m. on Tuesday, Aug. 9. 
  • When finished Tuesday morning, traffic control will be in place and southbound will have at least one lane closed until the expansion joint work is done in October.  
  • Lane closures are expected on I-35 from 27th Street to the Cambridge Circle.  

Northbound I-35 bridge joint replacement includes the following:  

  • Northbound I-35 work is done in two phases.  
  • One lane of northbound I-35 closing at 7 p.m. Tuesday, Aug. 9 for traffic control setup.  
  • Northbound I-35 reduced to one lane beginning 9 p.m. Tuesday, Aug. 9 through 6 a.m. on Wednesday, Aug. 10.  
  • When finished Wednesday morning, traffic control will be in place and northbound will have at least one lane closed until the expansion joint work is done in October. 
  • Lane closures are expected on I-35 from 7th Street Trafficway to Jarboe Street.  
  • Ramp closures include the northbound on ramp from the Cambridge Circle to I-35 through the duration of the project; and the 7th Street Trafficway on ramp to northbound I-35 closing during phase two of the project.  

I-35, I-435 & U.S. 69 KC Scout DMS Board Retrofit Project 

WEEKDAY OVERNIGHT SHORT-TERM FULL ROAD CLOSURES: There will be varying lane and overnight needed as part of a KC Scout Dynamic Message Sign Retrofit Project to bring seven sign board’s internal operating systems up-to-date. Project work includes removal of the existing boards from the roadway which will then be moved to another location, so that new internal operating equipment can be installed within the signs. The signs will look exactly the same externally as only internal components are being replaced. Temporary message boards will be in place until these original boards are retrofitted and reinstalled. Each sign is expected to take approximately two weeks to be completed and reinstalled, weather permitting.  Overall project work is scheduled to be completed in December 2016. (NEW 7-14-16)

There are seven different DMS locations primarily in Johnson County with the exception of one location in Wyandotte County as follows:

Location 1: Northbound U.S.69 one-half a mile north of 135th Street/Santa Fe Street.
Location 2: Northbound I-35 one-quarter mile north of 127th Street. Scheduled for removal: July 14, 2016.
Location 3: Southbound I-35 one-half mile north of 95th Street. Scheduled for removal: July 18, 2016. 
Location 4: Northbound I-35 one-half mile north of 24th Street.
Location 5: Northbound and southbound I-35 one-half mile north of Roe Lane.
Location 6: Southbound I-435 one-quarter mile north of 79th Street.
Location 7: Eastbound I-435 one-quarter mile east of Mission Road.

I-35 from Southwest Boulevard to 95th Street Resurfacing Project

WEEKDAY/WEEKEND OVERNIGHT LANE CLOSURES: On Wednesday, March 23, weather permitting, a concrete pavement repair and asphalt overlay project will begin on a 10-mile stretch of northbound and southbound I-35 from 95th Street to Southwest Boulevard, including all adjacent interchange ramps (Johnson County). Crews will complete partial and full depth patching to the existing concrete pavement, followed by a 4-inch asphalt overlay on various sections, and all new permanent pavement markings. Work will take place overnight beginning at 8 p.m. and reopening to all traffic at 5 a.m. the following morning, daily, Wednesday and Thursday; and on weekends from 8 p.m. Friday through 8 a.m. Saturday; and from 8 p.m. Saturday through late Sunday afternoon. Project work is scheduled to be completed in Late October 2016. (NEW 3-10-16)

I-35 from 151st Street to Santa Fe Street/135th Street Pavement Reconstruction Project

TRAFFIC SHIFT: Northbound I-35 from 151st Street to Santa Fe Street/135th Street will be SHIFTED onto new northbound I-35 lanes sometime on Sunday, August 14. Traffic shift work will begin at 2 a.m. that morning and should be shifted by late afternoon or sooner. This means both northbound and southbound I-35 will be reduced to TWO OPEN LANES each direction on their respective sides of the roadway beginning on Sunday, August 14, as reconstruction work begins to remove the median crossovers and reconstruct the center barrier wall. Project work is scheduled to be completed in September 2016. (NEW 8-11-16) 

24/7 LONG-TERM DUAL RAMP CLOSURES: Old U.S. 56 to northbound I-35 entrance ramp will be FULLY CLOSED, 24/7 round the clock, beginning at 4 a.m. on Tuesday, March 29 through late September 2016. Northbound I-35 to Santa Fe Street/135th Street exit ramp will be FULLY CLOSED, 24/7 round the clock, sometime during the day on Tuesday, March 29, through late September 2016. A marked detour will be provided.  Old U.S. 56 traffic will detour either northbound K-7 to eastbound K-10 or southbound on K-7 to 151st Street to access northbound I-35. Northbound I-35 traffic will detour via eastbound 119th Street to southbound Strang Line Road or via eastbound 151st Street to northbound Mur-Len Road to access Santa Fe Street/135th Street.  Project work is scheduled to be completed in late September 2016. (NEW 3-29-16)

24/7 LONG-TERM RAMP CLOSURE: Santa Fe Street/135th Street to southbound I-35 entrance ramp will be FULLY CLOSED, 24/7 round the clock, beginning at 2 a.m. on Tuesday, March 22, weather permitting,through late September 2016. A marked detour will be provided. See detour map above. Santa Fe Street/135th Street traffic will detour via southbound Mur-Len Road to westbound 151st Street or via northbound Ridgeview Road to eastbound 119th Street to access southbound I-35. Project work is scheduled to be completed in late September 2016. (NEW 3-29-16)

K-10 Eastbound over Sunflower Road Bridge Repair Project

TRAFFIC SHIFT &  24/7 LONG-TERM LANE CLOSURE: Eastbound K-10 LEFT LANE over the Sunflower Road Bridge and on either side of the bridge CLOSED, 24/7 round the clock, for repair work beginning TOMORROW, Thursday, August 11 through November 2016, weather permitting. Crews have completed all repair work on the right lane over the bridge and will now switch traffic in order to complete repair work on the left lane of the bridge. Project work is scheduled to be completed in November 2016. (REV. 8-10-16)

U.S. 69 from Blue Valley Parkway to 215th Street KC Scout Expansion Project

WEEKDAY WORK & SHOULDER IMPACTS: On Monday, February 15, a project will begin to expand the KC Scout dynamic message signs and cameras along U.S. 69 from the Blue Valley Parkway ramp to 215th Street. The majority of the project work will take place beyond the roadway shoulders on the highway right of way. There may be some occasional shoulder closures. Drivers should expect only minimal delays, primarily minor impacts only from trucks entering and leaving the project work zone throughout the project duration. Project work is scheduled to be completed by mid-July 2016. (NEW 2-15-16)

U.S. 69 Over 119th Street Bridge Repair Project

24/7 LONG-TERM LANE CLOSURE: Northbound U.S. 69 RIGHT LANE over the 119th Street Bridge CLOSED, 24/7 round the clock, beginning at 9 a.m. on Tuesday, July 5, throughout the project duration. Project work is scheduled to be completed in late November 2016. (REV. 7-1-16) 

U.S. 69 Northbound Blue River Bridge Replacement Project

24/7 LONG-TERM RAMP CLOSURE: 179th Street to northbound U.S. 69 entrance ramp CLOSED for adjacent bridge overlay work, 24/7 round the clock, beginning at 7:30 a.m. on Thursday, June 2 throughout the project duration, weather permitting. A marked detour will be provided. 179th Street ramp traffic will detour via southbound U.S. 69 to 199th Street exit and then back on northbound U.S. 69 to 179th street exit. Project work is scheduled to be completed in late November 2016. (NEW 6-1-16) 

24/7 LONG-TERM LANE CLOSURES: Northbound and southbound U.S. 69 over the Blue River Bridge will continue to be reduced to one lane each direction, placed side-by-side on the southbound U.S. 69 bridge,  throughout the project duration. Northbound U.S. 69 traffic currently entering the work zone travels in the right lane, but after tomorrow’s traffic switch, northbound U.S. 69 traffic will enter the work zone in the left lane and then be moved into the right lane just north of the 179th Street Bridge, before they cross over to the southbound side of U.S. 69. Project work is scheduled to be completed in late November 2016. (NEW 6-1-16) 

 

LEAVENWORTH COUNTY

 

K-7/U.S. 73/4th Street & Poplar Avenue Intersection Improvement Project 

24/7 ROAD & LANE CLOSURES: Northbound K-7/U.S. 73/4th Street from Pennsylvania Street to Linn Street will be reduced to ONE OPEN LANE and Poplar Avenue from 2nd Street to 4th Street CLOSED, 24/7 round the clock, beginning at 9 a.m. on Monday, June 27 throughout the project duration. Traffic will follow a marked detour via southbound Spruce Street or northbound Marion Street to 2nd Street to access Poplar Avenue. Later in the project during Phase Two construction, southbound K-7/U.S. 73/4th Street from Linn Street to Pennsylvania Street will be reduced to one open lane. Project work is scheduled to be completed in late Fall 2016. (NEW 6-24-16)

K-32 Over I-70/KTA Bridge Replacement Project

LONG-TERM FULL BRIDGE CLOSURE: Eastbound and westbound K-32 Bridge I-70/Kansas Turnpike will be FULLY CLOSED to all traffic for construction of a new replacement bridge beginning early morning on Monday, February 22 in Leavenworth County. On Monday, January 4, a replacement project began on the K-32 Bridge over I-70/Kansas Turnpike in Leavenworth County. Project work includes replacement of the existing 310-foot steel girder bridge (with 28-foot wide roadway) with a 325-foot welded plate girder bridge (with 47-foot wide roadway). Work will take place during daylight hours, Monday through Friday, with some occasional Saturday work. This KDOT bridge replacement construction project oversight will be managed in conjunction with our partner agency, the Kansas Turnpike Authority. Preliminary preparation work on the project began this past Monday, January 4. Beginning in late February 2016, eastbound and westbound K-32 over the I-70/KTA bridge will be closed to all traffic throughout the project duration. A marked detour will be provided. K-32 traffic will detour via K-7 north to U.S. 24/40 west and south back to K-32 and vice versa. Project work is scheduled to be completed in early January 2017. (REV. 4-29-16)

 

 

 

WYANDOTTE COUNTY

 

I-70 & I-635 Interchange Dual Bridge Repair Project

LONG-TERM LANE & RAMP CLOSURES: A dual bridge repair project will begin on I-70 and I-635 with the following closures taking place beginning at 11 p.m. on Wednesday, May 11 through the project duration. Project work is scheduled to be completed in early September 2016.  (REV. 5-10-16) 

Westbound I-70 over the Quarry Road  bridge will be reduced to two open lanes, 24/7 round the clock.

Southbound I-635 to westbound I-70 ramp CLOSED. Marked detour will be provided via K-32/Kansas Avenue west to Turner Diagonal. An optional detour will be State Avenue west to Turner Diagonal.

Northbound I-635 to westbound I-70 ramp CLOSED. Marked detour will be provided via K-32/Kansas Avenue west to Turner Diagonal. An optional detour will be State Avenue west to Turner Diagonal.  

I-435 at I-70 Interchange Multi-Bridge Repair Project

LONG-TERM LANE & RAMP CLOSURES: A multi-bridge repair project will begin on the I-435 bridges at the I-70 interchange with the following closures taking place beginning at 7 p.m. on Tuesday, May 10 through the project duration. Project work is scheduled to be completed in early October 2016.  (REV. 5-9-16) 

Northbound and southbound I-435 from north of I-70 to south of I-70 over the bridges will be reduced to two open lanes, 24/7 round the clock.

Westbound I-70 to southbound I-435 ramp CLOSED. Marked detour via westbound I-70 to northbound I-435 to westbound State Avenue to access southbound I-435. A suggested secondary detour route via 110th Street back to eastbound I-70 to 78th Street exit back to westbound I-70 to northbound I-435 to westbound State Avenue to access southbound I-435. 

U.S. 69 over Missouri River Bridge Replacement Project (MoDOT/KDOT Project) > #us69moriverbridge

24/7 LANE CLOSURES: Northbound and southbound U.S. 69 from I-635 (in Missouri) to Kindleberger Road in Kansas will be reduced to one lane in each direction, 24/7, beginning on Friday, October 24 for bridge replacement work. Both northbound and southbound U.S. 69 traffic will travel on the existing northbound U.S. 69 bridge (Platte Purchase Bridge). A crossover will be used to shift southbound U.S. 69 traffic to the existing Platte Purchase Bridge. The traffic switch is scheduled for Friday, October 31, 2014 and traffic will remain in this configuration until Thursday, December 1, 2016. Project work is scheduled to be completed on Thursday, December 1, 2016. (NEW 10-27-14)

U.S. 169 (Rainbow Boulevard)

WEEKDAY LANE CLOSURES: Northbound U.S. 169 Rainbow Boulevard at the West 39th Street Intersection will have varying lane closures for adjacent building construction beginning on Monday, September 28. Project work is scheduled to be completed in late May 2017. (NEW 9-28-15)

 

 

Links of Interest

JoCo Proj Webcam

Subscribe to Kansas City Metro Traffic and News Information

Lewis & Clark viaduct concept study

NE KDOT on facebook

KansasCityKDOT on Twitter

 TopekaMetroKDOT on Twitter

NEKansasKDOT on Twitter