KCMetroLogo

Daily Traffic Information

for the weekend of

Friday-Monday, April 17-20, 2015

 

(NEW - REVISED)

 


 

SHORT TERM

 

Short term project closures listed below typically take place during daylight hours. Project completion dates typically range from 1 to 30 days. All closures and scheduled work are weather permitting and subject to change.

 

JOHNSON COUNTY

  >  >  #Jocogateway

I-35 & I-435 Interchange Bridge Project

Traffic Pattern Change: Open southbound I-35 to THREE THROUGH LANES at I-435 on Friday, April 17 and northbound I-35 to THREE THROUGH LANES at I-435 on Saturday, April 18. (NEW 4-16-15)

Traffic Pattern Change: Northbound and southbound I-35 at I-435 will be reduced to TWO THROUGH LANES for 30 days beginning at 5:00 a.m. on Sunday, March 22 and will reopen to all traffic on Tuesday, April 21. Northbound I-35 left lane will be closed north of 119th Street and southbound I-35 right lane will become an exit-only lane to the westbound I-435 entrance ramp. Project work is scheduled to be completed on Tuesday, April 21. (NEW 3-20-15)

EXPECT DELAYS! WEEKDAY OVERNIGHT LANE CLOSURES: Northbound I-35 LEFT TWO LANES at I-435 will be CLOSED for traffic switch work beginning at 9:00 p.m. with one lane closed and at 10:00 p.m. two lanes closed on Friday, April 17 and reopening to all traffic at 8:00 a.m on Saturday, April 18. Project work is scheduled to be completed on Saturday, April 18. (NEW 4-17-15)

EXPECT DELAYS! WEEKDAY OVERNIGHT LANE CLOSURE: Southbound I-35 LEFT TWO LANES at I-435 will be CLOSED overnight for pavement marking work beginning at 10:00 p.m. on Friday, April 17 through 8:00 a.m. on Saturday, April 18. Project work is scheduled to be completed on Saturday, April 18. (NEW 4-17-15)

EXPECT DELAYS! WEEKDAY OVERNIGHT RAMP CLOSURES: Southbound I-35 to eastbound I-435 and southbound I-35 to westbound I-435 ramps will be CLOSED for traffic switch work beginning at 10:00 p.m. on Friday, April 17 and reopening to all traffic at 5:00 a.m on Saturday, April 18. Message boards will direct traffic to detour via southbound U.S. 69 to eastbound I-435 or westbound I-435. Project work is scheduled to be completed on Saturday, April. 18. (NEW 4-14-15)

EXPECT DELAYS! WEEKEND DAY OVERNIGHT LANE CLOSURE:  Northbound I-35 TWO LEFT LANES at I-435 will be CLOSED overnight for pavement marking work beginning at 10:00 p.m. on Saturday, April 18 and reopening to all traffic at 9:00 a.m. on Sunday, April 19. Project work is scheduled to be completed on Sunday, April 19. (NEW 4-16-15)

EXPECT DELAYS! WEEKEND DAY OVERNIGHT RAMP CLOSURE:  Northbound I-35 to westbound I-435 ramp will be CLOSED overnight for pavement marking work beginning at 10:00 p.m. on Saturday, April 18 and reopening to all traffic at 9:00 a.m. on Sunday, April 19. Project work is scheduled to be completed on Sunday, April 19. (NEW 4-16-15)

EXPECT DELAYS! WEEKDAY LANE CLOSURE:  Northbound I-35 LEFT LANE from I-435 to 95th Street will be CLOSED for asphalt work on Monday, April 20 between 9:00 a.m. and 3:00 p.m. Project work is scheduled to be completed on Monday, April 20. (NEW 4-16-15)

EXPECT DELAYS! WEEKDAY LANE CLOSURE: Eastbound I-435 RIGHT LANE from past I-35 to Quivira Road will be CLOSED for retaining wall work on Monday-Friday, April 20-24 between 9:00 a.m. and 3:00 p.m. Project work is scheduled to be completed on Friday, April 24. (NEW 4-17-15)

EXPECT DELAYS! WEEKDAY LANE CLOSURE: Westbound I-435 LEFT LANE at Quivira Road will be CLOSED for grading work on Monday-Friday, April 20-24 between 9:00 a.m. and 3:00 p.m. Project work is scheduled to be completed on Friday, April 24. (NEW 4-17-15)

K-10 & I-435 Interchange Bridge Project

No short-term project closures at this time.

K-10 & K-7 Interchange

No short-term project closures at this time.

K-10 & Ridgeview Road Interchange Bridge Project

No short-term project closures at this time.

K-10 & Renner Boulevard Interchange Project

No short-term project closures at this time.

Renner Boulevard at College Boulevard

EXPECT DELAYS! WEEKDAY LANE CLOSURE: Eastbound and westbound College Boulevard RIGHT LANES from Renner Boulevard to Ridgeview Boulevard will be CLOSED on Monday, April 20 between 9:00 a.m. and 3:00 p.m.  Turns will still be permitted via through lane. Project work is scheduled to be completed on Monday, April 20. (NEW 4-17-15)

EXPECT DELAYS! WEEKDAY LANE CLOSURE: Eastbound College Boulevard LEFT LANE before Ridgeview Road intersection will be CLOSED on Monday, April 20 between 9:00 a.m. and 3:00 p.m.  Turns will still be permitted via through lane. Project work is scheduled to be completed on Monday, April 20. (NEW 4-17-15)

Ridgeview Road at College Boulevard

EXPECT DELAYS! WEEKDAY LANE CLOSURE: Southbound Ridgeview Road RIGHT LANE at College Boulevard will be CLOSED for asphalt work on Monday, April 20 between 9:00 a.m. and 3:00 p.m. Turns will still be permitted via through lane. Project work is scheduled to be completed on Monday, April 20. (NEW 4-17-15)

Santa Fe Trail Drive

EXPECT DELAYS! 24/7 10-DAY FULL CLOSURE: Santa Fe Trail Drive under the I-435 bridges will be CLOSED to all traffic for drainage work, 24/7, for 10 days beginning at 5:00 a.m. on Monday, April 6 and will reopen to all traffic on Saturday, April 18. A marked detour will be provided. Santa Fe Trail Drive traffic will detour via 101st Terrace to Lackman Road to 105th Street. Project work is scheduled to be completed on Saturday, April 18. (REV. 4-17-15)


I-35 Pavement Reconstruction Project

EXPECT DELAYS! WEEKEND DAY LANE & RAMP CLOSURES:  The project work for this weekend, April 18-19, is still a go and the lane and ramp closures are now scheduled to begin on Sunday, April 19 as follows:

At 4:00 a.m. on Sunday, April 19, the southbound I-35 lanes will be shifted to the northbound side of the highway. All I-35 traffic will be carried on the existing northbound lanes separated by concrete barrier while the southbound lanes are reconstructed. Once the mainline traffic has been switched at approximately 11:00 a.m. on Sunday, April 19, the Santa Fe Street/135th Street to southbound I-35 entrance ramp and the southbound I-35 to Old U.S. 56 exit ramp will be CLOSED to all traffic. Marked detours will be provided for the ramp closures.

> > SPECIAL NOTE > > In the event of rain of Sunday, April 19, the lane and ramp closures will then be rescheduled for Monday, April 20 as follows.

At 4:00 a.m. on Monday, April 20, one lane of southbound I-35 will be shifted to the northbound side of the highway, then at 9:00 a.m. on Monday, April 20, the second lane of southbound I-35 will be shifted to the northbound side of the highway. All I-35 traffic will be carried on the existing northbound lanes separated by concrete barrier while the southbound lanes are reconstructed. Once the mainline traffic has been switched at approximately 11:00 a.m. on Monday, April 20, the Santa Fe Street/135th Street to southbound I-35 entrance ramp and the southbound I-35 to Old U.S. 56 exit ramp will be CLOSED to all traffic. Marked detours will be provided for the ramp closures.(NEW 4-17-15)

I-435 Sign Replacement Project

EXPECT DELAYS! WEEKDAY OVERNIGHT LANE CLOSURES: Westbound I-435 from Stateline Road to U.S. 69  will have varying lane closures for sign replacement work overnight beginning at 7:00 p.m. and reopening at 5:00 a.m. the following morning on Monday-Friday, March 30-April 24. Project work is scheduled to be completed on Friday, April 24. (NEW 3-27-15) 

I-435

EXPECT MAJOR DELAYS! WEEKDAY MOVING LANE CLOSURES: Eastbound and westbound I-435 from U.S. 69 to State Line Road will have varying lane closures via a mobile operation for spray patch pothole repair work on Monday-Wednesday, April 20-22 between 9:00 a.m. and 3:00 p.m. Project work is scheduled to be completed on Wednesday, April 22. (NEW 4-17-15) 

U.S. 56 / Shawnee Mission Parkway

EXPECT MAJOR DELAYS! WEEKDAY MOVING LANE CLOSURES: Eastbound and westbound U.S. 56 / Shawnee Mission Parkway from I-35 to State Line Road will have varying lane closures via a mobile operation for spray patch pothole repair work on Monday-Wednesday, April 20-22 between 9:00 a.m. and 3:00 p.m. Project work is scheduled to be completed on Wednesday, April 22. (NEW 4-17-15) 

 

 

LEAVENWORTH COUNTY

 

K-92 Centennial Bridge

EXPECT DELAYS! UPCOMING WEEKDAY FULL BRIDGE CLOSURE: Eastbound and westbound K-92 over the Centennial Bridge will be CLOSED to all traffic for bridge inspection work on Wednesday, April 22 between 9:00 a.m. and 3:30 p.m. No marked detours provided.  Project work is scheduled to be completed on Wednesday, April 22. (NEW 4-14-15) 

EXPECT DELAYS! UPCOMING WEEKDAY LANE CLOSURES: Eastbound and westbound K-92 over the Centennial Bridge will be reduced to one lane for both directions for bridge inspection work on Thursday, April 23 between 9:00 a.m. and 3:30 p.m. Flaggers will direct traffic across the bridge. Project work is scheduled to be completed on Thursday, April 23. (NEW 4-14-15) 

EXPECT DELAYS! UPCOMING WEEKDAY LANE CLOSURES: Eastbound and westbound K-92 over the Centennial Bridge will be reduced to one lane for both directions for bridge inspection work on Monday-Wednesday, April 27-29 between 9:00 a.m. and 3:30 p.m. each day. Flaggers will direct traffic across the bridge. Project work is scheduled to be completed on Wednesday, April 29. (NEW 4-14-15) 

Missouri Route: I-29  > > KCI Airport Travel Impacts

EXPECT DELAYS! 24/7 LANE & RAMP CLOSURES: Motorists should prepare for delays as MoDOT crews work to rehabilitate 12 bridges along the I-29 corridor between I-435 and I-635 in Platte County, MO beginning on Monday, April 20 and continuing for 6 months. Work will cause lane reductions, narrow lanes, and ramp closures. Motorists should use alternate routes such as I-435 and U.S. 169. The following impacts will be underway: 

  • Two lanes of I-29 will be maintained in each direction between 112th Street and Route 45 (64th Street).
  • I-29 will be reduced to one lane at Route D (Cookingham Drive) for each direction for 80 calendar days.
  • The ramp from eastbound Route 152 to southbound I-29 will be closed for the duration of the project.
  • I-29 lanes will be narrowed at the bridge locations.

Temporary lane closures may be encountered on Route D (Cookingham Drive), 112th Street, Tiffany Springs Parkway, Barry Road, 72nd Street, and Route 45 (64th Street) during off peak hours. Project work is scheduled to be completed in Fall 2015. (NEW 4-6-15)

 

 

WYANDOTTE COUNTY

  

 

No short-term project closures at this time.

 

 


  

LONG TERM

  

Long term project closures listed below typically take place 24 hours a day, 7 days a week. Project completion dates typically range from 31 days up to a year. All closures and scheduled work are weather permitting and subject to change.

 

JOHNSON COUNTY 

 

 > > #Jocogateway 

Westbound I-435 from U.S. 69 to I-35

TRAFFIC SHIFT: Westbound I-435 traffic from U.S. 69 to just west of I-35 will be shifted to the south with three through and one auxiliary lane for reconstruction work on the westbound I-435 lanes, 24/7 round the clock, beginning on Thursday, September 4 through late 2014, weather permitting. Crews will begin setting traffic control at 8:00 p.m. on Wednesday, September 3 and the traffic shift will be in place before morning rush hour on Thursday, September 4, weather permitting. 

Westbound I-435 traffic (from U.S. 69 to just west of I-35) will travel through the work zone via three through lanes and one auxiliary lane as follows: 

1) Far left lane traffic will travel through the work zone only directed via concrete barrier on either side of the driving lane. Traffic will travel on an 11-foot wide driving lane with an approximate 2-foot left shoulder and 8-foot right shoulder (lane is located in former eastbound I-435 lane/median area).
2) Center lane traffic will travel through the work zone as normal
3) Right lane traffic will travel through the work zone as normal
4) Far right auxiliary lane will be used for traffic wishing to access the U.S. 69, Quivira Road and I-35 interchanges  

Advance message boards will alert drivers to the traffic shift. There will be an 11-foot lane width restriction and a 55 mph posted speed limit through the project work zone throughout the project duration. Note: Eastbound I-435 traffic through this area has already been shifted to the south slightly to accommodate the westbound I-435 traffic shift. All ramp access will remain open at the U.S. 69, Quivira Road and I-35 interchanges. Project work is scheduled to be completed in Spring 2015. (REV. 1-9-15)

K-10 & Renner Boulevard Interchange Project

EXPECT DELAYS! 24/7 ROAD & RAMP CLOSURES: All lanes of Renner Boulevard at K-10, eastbound K-10 to Renner Boulevard exit ramp and Renner Boulevard to eastbound K-10 entrance ramp will be CLOSED to all traffic, 24/7 round the clock, beginning sometime EARLY AFTERNOON on Tuesday, April 14, weather permitting. Renner Boulevard is scheduled to reopen in mid-September 2015, and the eastbound K-10  Renner Boulevard ramps are scheduled to reopening August 2015. SPECIAL NOTE: Renner Boulevard and the adjacent K-10 ramps will FULLY CLOSE once College Boulevard is opened to four-lanes of traffic which is planned for some time during the day nesxt Tuesday, April 14. Renner Boulevard at K-10 cannot fully close until College Boulevard is fully opened to four lanes of traffic. Marked detours will be provided. Project work is scheduled to be completed in Late Summer 2015. (REV. 4-13-15) 


I-35 from 151st Street to Santa Fe/135th Street Pavement Reconstruction Project
Overall project work is scheduled to be completed in December 2015

EXPECT DELAYS! 24/7 RAMP CLOSURES:  Northbound and southbound I-35 from just north of 151st Street to just north of Santa Fe Street/135th Street will have varying lane and ramp closures for reconstruction work beginning on Monday, March 16. Construction will be completed in two phases. Each phase will take approximately four months to complete, weather permitting. During the weeks of March 16-30, crews will begin project work by setting traffic control followed by construction of median crossovers located at either end of the project. Traffic impacts include lane reductions on I-35 and the closure of the Santa Fe Street/135th Street to southbound I-35 entrance ramp throughout the project duration. Ramp closures and lane reductions are tentatively scheduled to begin sometime around Monday, March 30, weather permitting. Phase One. All I-35 traffic will be carried on the existing northbound lanes separated by concrete barrier while the southbound lanes are reconstructed. During this phase, the southbound I-35 to Old U.S. 56 exit ramp will be closed. Southbound I-35 to Old U.S. 56 ramp traffic will detour via the U.S. 169/K-7 exit then north on K-7 to Old U.S. 56. Approximate timeframe for completion work on this phase: April-July 2015, weather permitting. Phase Two. All I-35 traffic will be carried on the newly completed southbound lanes separated by concrete barrier while the northbound lanes are reconstructed. During this phase, the Old U.S. 56 to northbound I-35 entrance ramp and the northbound I-35 to Santa Fe Street/135th Street exit ramp will be closed. Approximate timeframe for completion work on this phase: August-December 2015, weather permitting. Santa Fe Street/135th Street to southbound I-35 ramp traffic will detour via Mur-Len Road south to 151st Street west to I-35 or via Ridgeview Road north to 119th Street east to I-35. Project work is scheduled to be completed in late December 2015. (NEW 3-18-15)

U.S. 69 & 159th Street Interchange Project

EXPECT MAJOR DELAYS! 24/7 LANE CLOSURE: Northbound U.S. 69 from 167th Street to 159th Street will be reduced to ONE OPEN LANE for ramp lane construction work, 24/7 round the clock, beginning on Thursday, April 16 through late September 2015. Project work is scheduled to be completed in late September 2015. (NEW 4-6-15) 

24/7 LANE CLOSURE: Eastbound 159th left lane from Lowell Avenue to U.S. 69 will be CLOSED for bridge work beginning on Wednesday, March 4, 24/7 round the clock.  Project work is scheduled to be completed in Spring 2015. (NEW 3-4-15)

24/7 LANE CLOSURE: Westbound 159th left lane from Foster Street to U.S. 69 will be CLOSED for bridge work beginning on Friday, February 13, 24/7 round the clock.  Project work is scheduled to be completed in Spring 2015. (NEW 2-16-15)

WEEKDAY LANE/SHOULDER CLOSURES: Northbound and southbound U.S. 69 from 151st Street to 169th Street may have periodic lane and shoulder closures for ramp construction work beginning in September 2014 through late October 2015. KDOT partnered on a city-led project with the City of Overland Park for the U.S. 69 & 159th Street interchange expansion project. This expansion project includes the addition of interchange ramps to the existing intersection at U.S. 69 and 159th Street in Overland Park (Johnson County). The project work zone on northbound and southbound U.S. 69 will extend from 151st Street south to 169th Street throughout the duration of the project. Construction work, including periodic lane and shoulder closures, will primarily occur during daylight hours Monday through Friday. Project work is scheduled to be completed in late October 2015. (NEW 12-15-14)

 

 

LEAVENWORTH COUNTY

 

 No long-term project closures at this time.

 

 

WYANDOTTE COUNTY

 

I-70 Multi-Bridge Repair Project
Overall project work is scheduled to be completed in December 2015

EXPECT DELAYS! 24/7 LANE & RAMP CLOSURES: The following ramp closures will begin: northbound and southbound I-635 to eastbound I-70 and eastbound I-70 to Park Drive/Kaw Drive, 24/7 round the clock, beginning at 7:00 p.m. on Thursday, March 26 for bridge deck replacement and repair work. Marked detours will be provided. At 3:00 p.m. on Saturday, March 28, eastbound and westbound I-70 from just west of I-635 to just east of Kaw Drive will be reduced to two 11-foot lanes with no shoulders, 24/7 round the clock, throughout the project duration.The northbound and southbound I-635 to eastbound I-70 ramp closures will be in place, 24/7 round the clock, throughout the project duration. Project construction information, including general phasing, traffic impacts and marked detour route maps can be viewed at: I-70 over Kaw Drive Multi-Bridge Construction Project Handout. The eastbound I-70 to Park Drive/Kaw Drive ramp will reopen to traffic in July 2015. The overall project work is scheduled to be completed in late December 2015. (REV. 3-27-15)

U.S. 69 over Missouri River Bridge Replacement Project (MoDOT/KDOT Project) > #us69moriverbridge
Overall project work is scheduled to be completed in December 2016

24/7 LANE CLOSURES: Northbound and southbound U.S. 69 from I-635 (in Missouri) to Kindleberger Road in Kansas will be reduced to one lane in each direction, 24/7, beginning on Friday, October 24 for bridge replacement work. Both northbound and southbound U.S. 69 traffic will travel on the existing northbound U.S. 69 bridge (Platte Purchase Bridge). A crossover will be used to shift southbound U.S. 69 traffic to the existing Platte Purchase Bridge. The traffic switch is scheduled for Friday, October 31, 2014 and traffic will remain in this configuration until Thursday, December 1, 2016. Project work is scheduled to be completed on Thursday, December 1, 2016. (NEW 10-27-14)