KCMetroLogo

Daily Traffic Information

 

for the weekend of

 

Friday - Monday, July 29 - August 1, 2016

 


 

SHORT-TERM

 

Short-term project closures listed below typically take place during daylight hours. Project completion dates typically range from 1 to 30 days. All closures and scheduled work are weather permitting and subject to change.

 

 

JOHNSON COUNTY 

 Johnson County Gateway  >   #jocogateway    

I-35/I-435/K-10

 

WEEKDAY OVERNIGHT SLOW MOVING ROAD CLOSURES: There will be varying lane/full roadway SHORT-TERM CLOSURES via a rolling roadblock on I-35, I-435 and K-10 for survey work overnight beginning at 9 p.m. on Thursday, July 28 and reopening to at 5 a.m. on Friday, July 29. Project work is scheduled to be completed on Friday, July 29. (NEW 7-28-16)

I-35 & I-435 Interchange 

24/7 SHORT-TERM LANE CLOSURES: Northbound and southbound I-35 FAR LEFT LANE at the I-435 interchange CLOSED for bridge reconstruction work, 24/7 round the clock, beginning at 5 a.m. on Monday, June 13 through 5 a.m. on Saturday, August 6 for northbound I-35 left lane and through 5 a.m. on Friday, July 30 for southbound I-35 left lane, weather permitting. These closures are needed so crews can widen the two bridges (to add an extra lane) to carry traffic on eastbound I-435 over I-35 and westbound I-435 over I-35. See photo above for the two interchange bridge locations where widening work is occurring. The reopening of these I-35 left lanes was delayed due to ongoing adjacent work in the area, but will reopen later this week and next week (as noted above), weather permitting. Project work is scheduled to be completed on Saturday, August 6. (REV. 7-26-16)

WEEKDAY SLOW MOVING RAMP CLOSURE: Northbound/westbound I-435 at K-10 to have SLOWDOWNS via a rolling roadblock for blasting work to remove rock at 2 p.m. on Tuesday-Friday, July 26-29. Project work is scheduled to be completed on Friday, July 29. (NEW 7-25-16)

WEEKEND DAY LANE CLOSURE: Northbound I-35 RIGHT LANE at 95th Street CLOSED for paving operations on Saturday, July 30 between 7 a.m. and 5 p.m. Project work is scheduled to be completed on Saturday, July 30. (NEW 7-27-16)

WEEKDAY OVERNIGHT RAMP CLOSURE: Southbound I-35 to westbound I-435 ramp CLOSED for pavement marking work beginning at 11:30 p.m. on Friday, July 29 and reopening at 5 a.m. on Saturday, July 30. Marked detour via early exit to southbound U.S. 69 to westbound I-435 and/or late exit via 119th Street back onto northbound I-35 to access westbound I-435. Project work is scheduled to be completed on Saturday, July 30. (NEW 7-26-16)

WEEKDAY OVERNIGHT LANE CLOSURES: Southbound I-35 TWO LEFT LANES from 95th Street to I-435 CLOSED for pavement marking work one lane beginning at 8 p.m. and a second left lane beginning at 10 p.m. on Friday, July 29 and reopening at 5 a.m. on Saturday, July 30. Project work is scheduled to be completed on Saturday, July 30(NEW 7-26-16)

Westbound I-435 to Northbound I-35 Ramp Long-Term 60-Day Closure

60-DAY LONG-TERM RAMP CLOSURE: Westbound I-435 to northbound I-35 entrance ramp CLOSED for ramp reconstruction work, 24/7 round the clock, beginning at 6 a.m. on Tuesday, May 31 and reopening by 5 a.m. on Thursday, August 4. Westbound I-435 marked detour via northbound U.S. 69 to access northbound I-35. Project work is scheduled to be completed on Thursday, August 4. (REV. 7-26-16)

K-10, I-435 & Lackman Road Interchange

OVERNIGHT FULL ROAD CLOSURES: Northbound and southbound Lackman Road at I-435 FULLY CLOSED overnight for demolition work on the former westbound I-435 Bridge beginning at 8 p.m. on Wednesday, July 27 and reopening at 5 a.m. on Thursday, July 28. Lackman Road traffic will detour via 105th Street to Santa Fe Trail Drive to 101st Terrace. Access to eastbound I-435 on- and off-ramps will remain available from the south side of the Lackman Road closure. Demolition work will be accomplished by heavy equipment picking away at the bridge structure. Project work is scheduled to be completed on Thursday, July 28. (REV. 7-25-16)

WEEKDAY OVERNIGHT LANE CLOSURES: Northbound and southbound Lackman Road LEFT LANES at I-435 CLOSED for bridge demolition work on the eastbound I-435 bridge beginning at 8 p.m. on Thursday-Friday, July 28-29 through 5 a.m. on Friday, July 29 and 10 a.m. on Saturday, July 30. Project work is scheduled to be completed on Saturday, July 30. (NEW 7-27-16)


I-35 from Southwest Boulevard to 95th Street Resurfacing Project

WEEKDAY/WEEKEND DAY OVERNIGHT LANE & RAMP CLOSURES:  The following I-35 lane and ramps CLOSED for resurfacing work. (NEW 7-27-16)  

> > > > SPECIAL NOTE > > > > Due to potential traffic delays, the contractor will now place additional variable message boards on I-35, U.S. 69 and I-435, as needed, to provide drivers advance warning of these delays so that they may utilize alternate routes. Drivers should expect significant delays when roadway is reduced to ONE OPEN LANE overnight and may wish to use alternate routes. 

8 p.m. Thursday, July 28 to 5 a.m. Friday, July 29

NB I-35 LEFT TWO LANES from 87th Street to 75th Street CLOSED. ONE THROUGH LANE OPEN.

NB I-35 RIGHT TWO LANES from Lamar Avenue to Southwest Boulevard CLOSED. ONE THROUGH LANE OPEN.

Ramp Closures:
67th Street to NB I-35 entrance ramp CLOSED.
Antioch Road to SB I-35 entrance ramp CLOSED. 

8 p.m. Friday, July 29 to 8 a.m. Saturday, July 30

NB I-35 LEFT TWO LANES from 75th Street to Johnson Drive CLOSED. TWO THROUGH LANES OPEN.

NB I-35 LEFT TWO LANES from Lamar Avenue to Southwest Boulevard CLOSED. ONE THROUGH LANE OPEN.

SB I-35 LEFT TWO LANES from Antioch Road to 75th Street CLOSED. TWO THROUGH LANES OPEN.

Ramp Closures:
67th Street to NB I-35 entrance ramp CLOSED.
SB I-35 to Johnson Drive exit ramp CLOSED.

7 p.m. Saturday, July 30 to 5 p.m. Sunday, July 31

NB I-35 LEFT TWO LANES from Johnson Drive to I-635 CLOSED. TWO THROUGH LANES OPEN.

NB I-35 LEFT TWO LANES from Lamar Avenue to Southwest Boulevard CLOSED. ONE THROUGH LANE OPEN.

SB I-35 LEFT TWO LANES from Antioch Road to 75th Street CLOSED. TWO THROUGH LANES OPEN.

Ramp Closures:
I-635 to NB I-35 entrance ramp CLOSED.
SB I-635 to NB I-35 entrance ramp CLOSED. 

I-35

WEEKDAY LANE CLOSURES: The following lane/ramp closures will take place to install conduit on the 159th Street Bridge over I-35 the week of August 1-4, weather permitting. This work is being done as part of the City of Olathe’s improvements on 159th Street between I-35 and Old US-56. (NEW 7-28-16)

Monday, August 1: SB I-35 right shoulder at 159th Street CLOSED.
Tuesday, August 2 5 a.m.-3 p.m.: SB I-35 TWO LEFT LANES with varying lane shifts CLOSED.
Wednesday, August 3: SB I-35 left shoulder and NB LEFT LANE CLOSED. The left lane is already closed under current I-35 construction project.
Thursday, August 4, 9 a.m.-3 p.m.: NB I-35 TWO LEFT LANES with varying lane shifts CLOSED. Lone Elm Road to NB I-35 ramp CLOSED.

I-435

WEEKDAY PARTIAL RAMP LANE CLOSURE: 95th Street to northbound I-435 ramp lane partially shifted onto shoulder for spray patching operations on Wednesday-Friday, July 27-29 between 9 a.m. and 3:30 p.m. Project work is scheduled to be completed on Friday, July 29. (NEW 7-26-16)

 

 

 

LEAVENWORTH COUNTY

  

 

No short-term project closures at this time.

 

WYANDOTTE COUNTY

 

I-435

WEEKDAY LANE CLOSURES: Northbound and southbound I-435 reduced to TWO OPEN LANES from Kansas River to Missouri River for pothole patching via a mobile operation on Tuesday-Friday, July 26-29 between 9 a.m. and 3:30 p.m. Project work is scheduled to be completed on Friday, July 29. (NEW 7-25-16) 

Northbound I-435 at I-70 Interchange Multi-Bridge Repair Project 

WEEKDAY LANE CLOSURES: Northbound I-435 from Kansas Avenue to just south of State Avenue will be reduced to ONE OPEN LANE so crews can switch traffic control on the bridge for continued repair work this Friday, July 29 between 10 a.m. and 2 p.m., weather permitting.  

RAMP REOPENING SOON: Once the traffic control switch work noted above is completed, the eastbound I-70 to northbound I-435 will REOPEN to unrestricted traffic and northbound I-435 from just north of Kansas Avenue to just south of I-70 will REOPEN to two lanes (one lane closed) by 2 p.m. on Friday, July 29, weather permitting through the project duration.(NEW 7-26-16)

Merriam Lane Pavement Replacement Project

24/7 LANE CLOSURES: Eastbound Merriam Lane will be CLOSED and detoured onto I-35 exiting at Lamar Avenue/24th Street. Westbound Merriam Lane will have ONE OPEN LANE for approximately 30 days beginning on Tuesday, July 5. Once the eastbound lanes are constructed, the traffic detour will flip, and the westbound traffic will be detoured onto I-35. Project work is scheduled to be completed in Summer 2016. (NEW 7-1-16)

 


  

LONG-TERM

  

Long-term project closures listed below typically take place 24 hours a day, 7 days a week. Project completion dates typically range from 31 days up to a year. All closures and scheduled work are weather permitting and subject to change.

 

 

JOHNSON COUNTY

 

 Johnson County Gateway  >   #Jocogateway 

I-35 & 95th Street Diverging Diamond Interchange Project

24/7 LONG-TERM INTERCHANGE CLOSURE: Northbound I-35 to 95th Street exit ramp and 95th Street to northbound I-35 entrance ramp CLOSED to all through traffic beginning at 10 p.m. on Sunday, February 21 through Late August 2016, as project work will take place to reconstruct the existing diamond interchange into a new diverging diamond interchange. Marked detour route maps can be found here: http://jocogateway.com/95th-street-and-i-35-diverging-diamond-interchange/  Project work is scheduled to be completed in late August 2016. (REV. 7-1-16)

K-10, I-435 & Lackman Road Interchange

LONG-TERM RAMP CLOSURES: Westbound I-435 to Lackman Road exit ramp CLOSED for westbound collector-distributor road construction work, 24/7 round the clock, beginning at 10 p.m. on Friday, July 15 through early October 2016, weather permitting. Westbound I-435 traffic will detour via southbound I-35 to westbound 95th Street to access southbound Lackman Road or via northbound I-435 to eastbound 95th Street to access Lackman Road. Project work is scheduled to be completed in October 2016  (NEW 7-8-16)

LONG-TERM RAMP CLOSURES: Lackman Road to westbound I-435 entrance ramp CLOSED for westbound collector-distributor road construction work, 24/7 round the clock, beginning at 10 p.m. on Friday, July 15 through early October 2016, weather permitting. Marked detours provided. Southbound Lackman Road traffic will detour via westbound College Boulevard to northbound Renner Boulevard to the K-10 interchange to access westbound I-435. Northbound Lackman Road traffic will detour via westbound 95th Street to the I-435 interchange.  Project work is scheduled to be completed in October 2016. (NEW 7-8-16)

I-35 & I-435 Interchange Long-Term Loop Ramp Closure 

24/7 LONG-TERM LOOP RAMP CLOSURE: Southbound I-35 to eastbound I-435 loop ramp CLOSED for pavement reconstruction and tie-in work, 24/7 round the clock, beginning at 10 p.m. on Monday, April 11 through late October 2016, weather permitting. SB I-35 to EB I-435 ramp traffic to detour via southbound I-35 to southbound U.S. 69 to eastbound I-435 or via eastbound 119th Street northbound I-35 to eastbound I-435. We recommend that drivers use the detour route via southbound U.S. 69, and NOT the eastbound 119th Street route. The eastbound 119th Street detour route is provided as a backup marked detour route for those drivers who miss the southbound U.S. 69 detour route. Project work is scheduled to be completed in Late October 2016. (REV. 3-24-16)


I-35, I-435 & U.S. 69 KC Scout DMS Board Retrofit Project 

WEEKDAY OVERNIGHT SHORT-TERM FULL ROAD CLOSURES: There will be varying lane and overnight needed as part of a KC Scout Dynamic Message Sign Retrofit Project to bring seven sign board’s internal operating systems up-to-date. Project work includes removal of the existing boards from the roadway which will then be moved to another location, so that new internal operating equipment can be installed within the signs. The signs will look exactly the same externally as only internal components are being replaced. Temporary message boards will be in place until these original boards are retrofitted and reinstalled. Each sign is expected to take approximately two weeks to be completed and reinstalled, weather permitting.  Overall project work is scheduled to be completed in December 2016. (NEW 7-14-16)

There are seven different DMS locations primarily in Johnson County with the exception of one location in Wyandotte County as follows:

Location 1: Northbound U.S.69 one-half a mile north of 135th Street/Santa Fe Street.
Location 2: Northbound I-35 one-quarter mile north of 127th Street. Scheduled for removal: July 14, 2016.
Location 3: Southbound I-35 one-half mile north of 95th Street. Scheduled for removal: July 18, 2016. 
Location 4: Northbound I-35 one-half mile north of 24th Street.
Location 5: Northbound and southbound I-35 one-half mile north of Roe Lane.
Location 6: Southbound I-435 one-quarter mile north of 79th Street.
Location 7: Eastbound I-435 one-quarter mile east of Mission Road.

I-35 from Southwest Boulevard to 95th Street Resurfacing Project

WEEKDAY/WEEKEND OVERNIGHT LANE CLOSURES: On Wednesday, March 23, weather permitting, a concrete pavement repair and asphalt overlay project will begin on a 10-mile stretch of northbound and southbound I-35 from 95th Street to Southwest Boulevard, including all adjacent interchange ramps (Johnson County). Crews will complete partial and full depth patching to the existing concrete pavement, followed by a 4-inch asphalt overlay on various sections, and all new permanent pavement markings. Work will take place overnight beginning at 8 p.m. and reopening to all traffic at 5 a.m. the following morning, daily, Wednesday and Thursday; and on weekends from 8 p.m. Friday through 8 a.m. Saturday; and from 8 p.m. Saturday through late Sunday afternoon. Project work is scheduled to be completed in Late October 2016. (NEW 3-10-16)

I-35 from 151st Street to Santa Fe Street/135th Street Pavement Reconstruction Project

24/7 TRAFFIC SHIFT: All northbound I-35 traffic will be shifted onto the southbound I-35 lanes by 3 p.m. on Tuesday, March 29, weather permitting, through late September 2016. Both northbound and southbound I-35 will be reduced to two lanes each direction in the final traffic configuration throughout the project duration. Project work is scheduled to be completed in late September 2016. (NEW 3-29-16)

24/7 LONG-TERM DUAL RAMP CLOSURES: Old U.S. 56 to northbound I-35 entrance ramp will be FULLY CLOSED, 24/7 round the clock, beginning at 4 a.m. on Tuesday, March 29 through late September 2016. Northbound I-35 to Santa Fe Street/135th Street exit ramp will be FULLY CLOSED, 24/7 round the clock, sometime during the day on Tuesday, March 29, through late September 2016. A marked detour will be provided.  Old U.S. 56 traffic will detour either northbound K-7 to eastbound K-10 or southbound on K-7 to 151st Street to access northbound I-35. Northbound I-35 traffic will detour via eastbound 119th Street to southbound Strang Line Road or via eastbound 151st Street to northbound Mur-Len Road to access Santa Fe Street/135th Street.  Project work is scheduled to be completed in late September 2016. (NEW 3-29-16)

24/7 LONG-TERM RAMP CLOSURE: Santa Fe Street/135th Street to southbound I-35 entrance ramp will be FULLY CLOSED, 24/7 round the clock, beginning at 2 a.m. on Tuesday, March 22, weather permitting,through late September 2016. A marked detour will be provided. See detour map above. Santa Fe Street/135th Street traffic will detour via southbound Mur-Len Road to westbound 151st Street or via northbound Ridgeview Road to eastbound 119th Street to access southbound I-35. Project work is scheduled to be completed in late September 2016. (NEW 3-29-16)

K-10 Eastbound over Sunflower Road Bridge Repair Project

24/7 LONG-TERM LANE CLOSURE: Eastbound K-10 RIGHT LANE over the Sunflower Road Bridge and on either side of the bridge CLOSED, 24/7 round the clock, for repair work beginning on Monday, June 6 through November 2016. Project work is scheduled to be completed in November 2016. (NEW 6-3-16) 

U.S. 69 from Blue Valley Parkway to 215th Street KC Scout Expansion Project

WEEKDAY WORK & SHOULDER IMPACTS: On Monday, February 15, a project will begin to expand the KC Scout dynamic message signs and cameras along U.S. 69 from the Blue Valley Parkway ramp to 215th Street. The majority of the project work will take place beyond the roadway shoulders on the highway right of way. There may be some occasional shoulder closures. Drivers should expect only minimal delays, primarily minor impacts only from trucks entering and leaving the project work zone throughout the project duration. Project work is scheduled to be completed by mid-July 2016. (NEW 2-15-16)

U.S. 69 Over 119th Street Bridge Repair Project

24/7 LONG-TERM LANE CLOSURE: Northbound U.S. 69 RIGHT LANE over the 119th Street Bridge CLOSED, 24/7 round the clock, beginning at 9 a.m. on Tuesday, July 5, throughout the project duration. Project work is scheduled to be completed in late November 2016. (REV. 7-1-16) 

U.S. 69 Northbound Blue River Bridge Replacement Project

24/7 LONG-TERM RAMP CLOSURE: 179th Street to northbound U.S. 69 entrance ramp CLOSED for adjacent bridge overlay work, 24/7 round the clock, beginning at 7:30 a.m. on Thursday, June 2 throughout the project duration, weather permitting. A marked detour will be provided. 179th Street ramp traffic will detour via southbound U.S. 69 to 199th Street exit and then back on northbound U.S. 69 to 179th street exit. Project work is scheduled to be completed in late November 2016. (NEW 6-1-16) 

24/7 LONG-TERM LANE CLOSURES: Northbound and southbound U.S. 69 over the Blue River Bridge will continue to be reduced to one lane each direction, placed side-by-side on the southbound U.S. 69 bridge,  throughout the project duration. Northbound U.S. 69 traffic currently entering the work zone travels in the right lane, but after tomorrow’s traffic switch, northbound U.S. 69 traffic will enter the work zone in the left lane and then be moved into the right lane just north of the 179th Street Bridge, before they cross over to the southbound side of U.S. 69. Project work is scheduled to be completed in late November 2016. (NEW 6-1-16) 

 

LEAVENWORTH COUNTY

 

K-7/U.S. 73/4th Street & Poplar Avenue Intersection Improvement Project 

24/7 ROAD & LANE CLOSURES: Northbound K-7/U.S. 73/4th Street from Pennsylvania Street to Linn Street will be reduced to ONE OPEN LANE and Poplar Avenue from 2nd Street to 4th Street CLOSED, 24/7 round the clock, beginning at 9 a.m. on Monday, June 27 throughout the project duration. Traffic will follow a marked detour via southbound Spruce Street or northbound Marion Street to 2nd Street to access Poplar Avenue. Later in the project during Phase Two construction, southbound K-7/U.S. 73/4th Street from Linn Street to Pennsylvania Street will be reduced to one open lane. Project work is scheduled to be completed in late Fall 2016. (NEW 6-24-16)

K-32 Over I-70/KTA Bridge Replacement Project

LONG-TERM FULL BRIDGE CLOSURE: Eastbound and westbound K-32 Bridge I-70/Kansas Turnpike will be FULLY CLOSED to all traffic for construction of a new replacement bridge beginning early morning on Monday, February 22 in Leavenworth County. On Monday, January 4, a replacement project began on the K-32 Bridge over I-70/Kansas Turnpike in Leavenworth County. Project work includes replacement of the existing 310-foot steel girder bridge (with 28-foot wide roadway) with a 325-foot welded plate girder bridge (with 47-foot wide roadway). Work will take place during daylight hours, Monday through Friday, with some occasional Saturday work. This KDOT bridge replacement construction project oversight will be managed in conjunction with our partner agency, the Kansas Turnpike Authority. Preliminary preparation work on the project began this past Monday, January 4. Beginning in late February 2016, eastbound and westbound K-32 over the I-70/KTA bridge will be closed to all traffic throughout the project duration. A marked detour will be provided. K-32 traffic will detour via K-7 north to U.S. 24/40 west and south back to K-32 and vice versa. Project work is scheduled to be completed in early January 2017. (REV. 4-29-16)

 

 

WYANDOTTE COUNTY

 

I-70 & I-635 Interchange Dual Bridge Repair Project

LONG-TERM LANE & RAMP CLOSURES: A dual bridge repair project will begin on I-70 and I-635 with the following closures taking place beginning at 11 p.m. on Wednesday, May 11 through the project duration. Project work is scheduled to be completed in early September 2016.  (REV. 5-10-16) 

Westbound I-70 over the Quarry Road  bridge will be reduced to two open lanes, 24/7 round the clock.

Southbound I-635 to westbound I-70 ramp CLOSED. Marked detour will be provided via K-32/Kansas Avenue west to Turner Diagonal. An optional detour will be State Avenue west to Turner Diagonal.

Northbound I-635 to westbound I-70 ramp CLOSED. Marked detour will be provided via K-32/Kansas Avenue west to Turner Diagonal. An optional detour will be State Avenue west to Turner Diagonal.  

I-435 at I-70 Interchange Multi-Bridge Repair Project

LONG-TERM LANE & RAMP CLOSURES: A multi-bridge repair project will begin on the I-435 bridges at the I-70 interchange with the following closures taking place beginning at 7 p.m. on Tuesday, May 10 through the project duration. Project work is scheduled to be completed in early October 2016.  (REV. 5-9-16) 

Northbound and southbound I-435 from north of I-70 to south of I-70 over the bridges will be reduced to two open lanes, 24/7 round the clock.

Eastbound I-70 to northbound I-435 ramp CLOSED. Marked detour via eastbound I-70 to 78th Street exit back to westbound I-70 to access northbound I-435.

Westbound I-70 to southbound I-435 ramp CLOSED. Marked detour via westbound I-70 to northbound I-435 to westbound State Avenue to access southbound I-435. A suggested secondary detour route via 110th Street back to eastbound I-70 to 78th Street exit back to westbound I-70 to northbound I-435 to westbound State Avenue to access southbound I-435. 

I-635 & K-5 Interchange Tower Lighting Project 

WEEKDAY SHOULDER CLOSURES: The I-635 and K-5 interchange will have intermittent shoulder closures for a high tower light replacement project beginning on Monday, April 4 through early June 2016. All adjacent interchange ramps will remain open. Project work is scheduled to be completed in early June 2016. (NEW 3-30-16)

U.S. 69 over Missouri River Bridge Replacement Project (MoDOT/KDOT Project) > #us69moriverbridge

24/7 LANE CLOSURES: Northbound and southbound U.S. 69 from I-635 (in Missouri) to Kindleberger Road in Kansas will be reduced to one lane in each direction, 24/7, beginning on Friday, October 24 for bridge replacement work. Both northbound and southbound U.S. 69 traffic will travel on the existing northbound U.S. 69 bridge (Platte Purchase Bridge). A crossover will be used to shift southbound U.S. 69 traffic to the existing Platte Purchase Bridge. The traffic switch is scheduled for Friday, October 31, 2014 and traffic will remain in this configuration until Thursday, December 1, 2016. Project work is scheduled to be completed on Thursday, December 1, 2016. (NEW 10-27-14)

U.S. 169 (Rainbow Boulevard)

WEEKDAY LANE CLOSURES: Northbound U.S. 169 Rainbow Boulevard at the West 39th Street Intersection will have varying lane closures for adjacent building construction beginning on Monday, September 28. Project work is scheduled to be completed in late May 2017. (NEW 9-28-15)

 

 

Links of Interest

JoCo Proj Webcam

Subscribe to Kansas City Metro Traffic and News Information

Lewis & Clark viaduct concept study

NE KDOT on facebook

KansasCityKDOT on Twitter

 TopekaMetroKDOT on Twitter

NEKansasKDOT on Twitter