Wednesday-Monday, December 23-29, 2014

 

(NEW - REVISED)

 


 

SHORT TERM

 

Short term project closures listed below typically take place during daylight hours. Project completion dates typically range from 1 to 30 days. All closures and scheduled work are weather permitting and subject to change.

 

JOHNSON COUNTY

> > #Jocogateway

I-35 & I-435 Interchange Bridge Project

EXPECT DELAYS! UPCOMING WEEKDAY LANE CLOSURE: Eastbound I-435 right lane from just past I-35 to Quivira Road will be CLOSED for retaining wall work on Tuesday, December 30 between 9:00 a.m. and 3:00 p.m.  Project work is scheduled to be completed on Tuesday, December 30. (NEW 12-23-14)

EXPECT DELAYS! UPCOMING WEEKDAY RAMP CLOSURE: Northbound I-35 to westbound I-435 ramp will be CLOSED for bridge work beginning at 10:00 p.m. on Tuesday, January 6, 2015 and will reopen to all traffic at 5:00 a.m. on Wednesday, January 7.  Project work is scheduled to be completed on Wednesday, January 7. (NEW 12-23-14)

K-10 & I-435 Interchange Bridge Project  

No short-term project closures at this time.

K-10 & Ridgeview Road Interchange Bridge Project

EXPECT DELAYS! UPCOMING WEEKDAY LANE CLOSURE: Northbound and southbound Ridgeview Road right lanes at College Boulevard will be CLOSED for traffic signal work on Tuesday, December 30 between 9:00 a.m. and 3:00 p.m. Project work is scheduled to be completed on Tuesday, December 30. (NEW 12-23-14) 

EXPECT DELAYS! UPCOMING WEEKDAY LANE CLOSURE: Northbound and southbound Ridgeview Road right lanes at College Boulevard will be CLOSED for traffic signal work on Wednesday, December 31 between 9:00 a.m. and NOON 12:00 p.m. Project work is scheduled to be completed on Wednesday, December 31. (NEW 12-23-14) 

Lackman Road

EXPECT DELAYS! WEEKDAY LANE CLOSURE: Northbound Lackman Road right turn lane at 105th Street will be CLOSED for signal work on Wednesday, December 24 between 9:00 a.m. and NOON 12:00 p.m. Right turns will be ALLOWED from the northbound Lackman Road right through lane onto 105th Street during this daytime lane closure. Project work is scheduled to be completed on Wednesday, December 24. (NEW 12-18-14) 

EXPECT DELAYS! UPCOMING WEEKDAY LANE CLOSURE: Northbound Lackman Road right turn lane at 105th Street will be CLOSED for signal work on Tuesday-Wednesday, December 29-30 between 9:00 a.m. and 3:00 p.m. Right turns will be ALLOWED from the northbound Lackman Road right through lane onto 105th Street during this daytime lane closure. Project work is scheduled to be completed on Wednesday, December 30. (NEW 12-23-14)

College Boulevard 

TRAFFIC SHIFT: Eastbound and westbound College Boulevard traffic from Ridgeview Road to Renner Boulevard will experience a traffic shift during the afternoon on Friday, October 31. Construction crews will shift traffic to the south side of College Boulevard in order to continue to work on the north side of College Boulevard.  The westbound lanes will move south. The eastbound lane will remain in the current location  and traffic will be ‘head to head’ (side by side) one lane each direction for this temporary traffic pattern.  Traffic entering College Boulevard from Ambassador and Penrose will be able to make both left and right hand turns at this time. Project work is scheduled to be completed in early January 2015. (REV. 11-21-14)

 

 

LEAVENWORTH COUNTY

 

U.S. 73 / K-7 Pavement Replacement Project
Overall project work is scheduled to be completed in late January 2015

24/7 LANE CLOSURES: Northbound and southbound U.S. 73/K-7 from 20th Street to the north junction of Leavenworth County Road 14/Santa Fe Trail will be CLOSED to all traffic beginning at 8:00 a.m. on Monday, July 7 for pavement replacement work. A marked detour will be provided via Leavenworth County Road 14. 

PROJECT UPDATE: REOPENING DELAYED. As of TODAY, Tuesday, December 16, the U.S. 73/K-7 pavement replacement and bridge repair project in Leavenworth County will not be completed and will not reopen to traffic in late December 2014, as originally planned. (See original news release below for more project information.) The primary contractor, KOSS Construction, has informed us that they will not be able to complete enough project work to safely open U.S. 73/K-7 to the traveling public this calendar year (2014).  

KOSS Construction plans to continue work on the project  through this Friday, December 19. From Friday, December 19, 2014 -Monday, January 5, 2015, KOSS Construction will suspend work on the project for the holiday season. They plan to be back to work on the project on Monday, January 5, 2015, weather permitting.

KOSS Construction plans to complete enough of the pavement work in January to open up the roadway to the traveling public by the end of the month, late January 2015, weather permitting. Once U.S. 73/K-7  reopens to the traveling public, the project will then be suspended for winter shutdown and work will resume in early to mid-April 2015, weather permitting.

Here’s what this means for drivers: The current detour will remain in place through late January 2015. Once the roadway is reopened to unrestricted traffic, the detour will be deactivated until April 2015.  Then sometime in April 2015, the detour will be reactivated and KOSS Construction will resume work on the project until all remaining work is completed. Project work is scheduled to be completed in late January 2015. (REV. 12-16-14)

 

 

WYANDOTTE COUNTY

 

I-70 & K-7 Interchange Project
Overall project work scheduled to be completed in late Fall 2014

TRAFFIC PATTERN CHANGE: The new westbound I-70 to southbound K-7 ramp opened to traffic at 9:00 a.m. on Monday, December 22. Since the new westbound I-70 to southbound K-7 loop ramp is now open to all traffic, sometime the week of December 29-January 2, weather permitting, the left turn lanes from the existing westbound I-70 to southbound K-7 ramp will be removed. Westbound I-70 traffic will no longer use this existing ramp to exit onto southbound K-7. At that point in time, the only movements available from the existing westbound I-70 to southbound K-7 ramp will be either right turns onto northbound K-7 or the through lane movement onto Canaan Drive. Once the left turn lanes on the existing ramp are removed, westbound I-70 traffic wanting to access southbound K-7 MUST use the new westbound I-70 to southbound K-7 loop ramp. Project work is scheduled to be completed on Friday, December 26. (REV. 12-23-14)

 

EXPECT DELAYS! WEEKDAY OVERNIGHT LANE CLOSURES: Westbound I-70 right lane at K-7 will be CLOSED for bridge girder removal work beginning at 9:00 p.m., Tuesday, December 23 and will reopen to all traffic by 5:00 a.m. Wednesday, December 24. Project work is scheduled to be completed on Wednesday, December 24. (NEW 12-22-14)

 

 


  

LONG TERM

  

Long term project closures listed below typically take place 24 hours a day, 7 days a week. Project completion dates typically range from 31 days up to a year. All closures and scheduled work are weather permitting and subject to change.

 

JOHNSON COUNTY 

 

 > > #Jocogateway 

Westbound I-435 from U.S. 69 to I-35

TRAFFIC SHIFT: Westbound I-435 traffic from U.S. 69 to just west of I-35 will be shifted to the south with three through and one auxiliary lane for reconstruction work on the westbound I-435 lanes, 24/7 round the clock, beginning on Thursday, September 4 through late 2014, weather permitting. Crews will begin setting traffic control at 8:00 p.m. on Wednesday, September 3 and the traffic shift will be in place before morning rush hour on Thursday, September 4, weather permitting. 

Westbound I-435 traffic (from U.S. 69 to just west of I-35) will travel through the work zone via three through lanes and one auxiliary lane as follows: 

1) Far left lane traffic will travel through the work zone only directed via concrete barrier on either side of the driving lane. Traffic will travel on an 11-foot wide driving lane with an approximate 2-foot left shoulder and 8-foot right shoulder (lane is located in former eastbound I-435 lane/median area).
2) Center lane traffic will travel through the work zone as normal
3) Right lane traffic will travel through the work zone as normal
4) Far right auxiliary lane will be used for traffic wishing to access the U.S. 69, Quivira Road and I-35 interchanges  

Advance message boards will alert drivers to the traffic shift. There will be an 11-foot lane width restriction and a 55 mph posted speed limit through the project work zone throughout the project duration. Note: Eastbound I-435 traffic through this area has already been shifted to the south slightly to accommodate the westbound I-435 traffic shift. All ramp access will remain open at the U.S. 69, Quivira Road and I-35 interchanges. Project work is scheduled to be completed in late 2014. (NEW 8-25-14)

College Boulevard

TRAFFIC SHIFT: Eastbound and westbound College Boulevard traffic from Ridgeview Road to Renner Boulevard will experience a traffic shift during the afternoon on Friday, October 31. Construction crews will shift traffic to the south side of College Boulevard in order to continue to work on the north side of College Boulevard.  The westbound lanes will move south. The eastbound lane will remain in the current location  and traffic will be ‘head to head’ (side by side) one lane each direction for this temporary traffic pattern.  Traffic entering College Boulevard from Ambassador and Penrose will be able to make both left and right hand turns at this time. Project work is scheduled to be completed in early January 2015. (REV. 11-21-14)


U.S. 69 & 159th Street Interchange

WEEKDAY LANE/SHOULDER CLOSURES: Northbound and southbound U.S. 69 from 151st Street to 169th Street may have periodic lane and shoulder closures for ramp construction work beginning in September 2014 through late October 2015. KDOT partnered on a city-led project with the City of Overland Park for the U.S. 69 & 159th Street interchange expansion project. This expansion project includes the addition of interchange ramps to the existing intersection at U.S. 69 and 159th Street in Overland Park (Johnson County). The project work zone on northbound and southbound U.S. 69 will extend from 151st Street south to 169th Street throughout the duration of the project. Construction work, including periodic lane and shoulder closures, will primarily occur during daylight hours Monday through Friday. Project work is scheduled to be completed in late October 2015. (NEW 12-15-14)

 

 

LEAVENWORTH COUNTY

 

 No long-term project closures at this time.

 

 

WYANDOTTE COUNTY

 

U.S. 69 over Missouri River Bridge Replacement Project (MoDOT/KDOT Project) > #us69moriverbridge
Overall project work is scheduled to be completed in December 2016

24/7 LANE CLOSURES: Northbound and southbound U.S. 69 from I-635 (in Missouri) to Kindleberger Road in Kansas will be reduced to one lane in each direction, 24/7, beginning on Friday, October 24 for bridge replacement work. Both northbound and southbound U.S. 69 traffic will travel on the existing northbound U.S. 69 bridge (Platte Purchase Bridge). A crossover will be used to shift southbound U.S. 69 traffic to the existing Platte Purchase Bridge. The traffic switch is scheduled for Friday, October 31, 2014 and traffic will remain in this configuration until Thursday, December 1, 2016. Project work is scheduled to be completed on Thursday, December 1 2016. (NEW 10-27-14)