Kansas Department of Transportation "...to provide a statewide transportation system to meet the needs of Kansas."
    
 
Kansas City Metro Area
Lane Closure Info

for

Friday, April 25, 2014

(NEW / REVISED)

SHORT TERM
Short term project closures listed below typically take place during daylight hours. Project completion dates typically range from 1 to 30 days, weather permitting.

JOHNSON COUNTY

I-35 

UPDATE! EXPECT DELAYS! WEEKDAY RAMP CLOSURE: Northbound I-35 to northbound I-635 ramp will be CLOSED for attenuator replacement work on Wednesday-Thursday Friday, April 23-24 25 between 9:00 a.m. and 3:00 p.m. each day. Due to the rain today, Thursday, April 24, the ramp will remain OPEN and the rescheduled closure for the ramp is now tomorrow, Friday, April 25. During the two-day ramp closure, northbound I-35 drivers should use the 18th Street Expressway interchange to exit and then head back southbound on I-35 to access the northbound I-635 ramp. Project work is scheduled to be completed on Friday, April 25. (Rev. 4-24-14)

K-7 at I-35 Pavement Replacement Project
Overall project work is scheduled to be completed by late September 2014

EXPECT DELAYS! UPCOMING FULL ROADWAY CLOSURE: Northbound and southbound K-7 will be CLOSED to through traffic between the northbound and southbound I-35 exit ramps for pavement replacement work beginning on Monday, April 28, sometime after morning rush hour, through mid-July 2014. A marked detour will be provided. Traffic will detour via the interchange ramps. Access will be maintained to local businesses throughout the project duration. This portion of the project work is scheduled to be completed in mid-July 2014. (New 4-23-14)

U.S. 69

EXPECT DELAYS! WEEKDAY RAMP LANE CLOSURE: Southbound U.S. 69 to 119th Street right ramp lane will be CLOSED for core drilling work on Thursday, April 24 between 9:00 a.m. and 3:00 p.m. each day. Project work is scheduled to be completed on Thursday, April 24. (New 4-23-14)

U.S. 69 Resurfacing Project from 199th Street to 143rd Street Bridge
Overall project work is scheduled to be completed by early May 2014

EXPECT MAJOR DELAYS! WEEKDAY LANE CLOSURES: Northbound U.S. 69 from 199th Street north in one-mile segments will have ONE OPEN LANE for milling and overlay work on Monday-Friday, April 21-25 daily between 6:00 a.m. and 8:00 p.m. Project work is scheduled to be completed on Friday, April 25. (New 4-18-14)

U.S. 169

EXPECT DELAYS! WEEKDAY MOBILE LANE CLOSURES: Northbound U.S. 169 right lane just south of 159th Street will be CLOSED for utility work on Monday-Friday, April 21-25 between 9:00 a.m. and 5:00 p.m. Project work is scheduled to be completed on Friday, April 25. (New 4-18-14)

LEAVENWORTH COUNTY

No project closures at this time.

WYANDOTTE COUNTY

I-70 at Riverview Avenue Bridge Replacement Project
Overall project work is scheduled to be completed by Spring 2014

No project closures at this time.

I-70 & K-7 Interchange Project
Overall project work scheduled to be completed in late Fall 2014

134th Street at I-70

24/7 ROADWAY CLOSURE: Northbound and southbound 134th Street from Kansas Avenue to Riverview Avenue will be CLOSED to all through traffic for bridge construction work, 24/7 round the clock, beginning at 6:00 a.m. on Monday, April 21 through 6:00 p.m. on Friday, April 25. No marked detour provided. Project work is scheduled to be completed on Friday, April 18. (New 4-15-14)

I-70 at 134th Street

RAINED OUT for Thursday, April 24! EXPECT DELAYS! WEEKDAY LANE CLOSURE: Westbound I-70 right lane at K-7 will be CLOSED for bridge work on Tuesday-Friday, April 22-25 between 9:00 a.m. and 3:30 p.m. Project work is scheduled to be completed on Friday, April 25. (Rev. 4-22-14)

RAINED OUT for Thursday, April 24! EXPECT DELAYS! WEEKDAY LANE CLOSURE: Eastbound I-70 right lane at 134th Street will be CLOSED for resurfacing work and setting concrete barriers on Friday, April 25 between 9:00 a.m. and 3:30 p.m. Project work is scheduled to be completed on Friday, April 25. (Rev. 4-24-14)

LONG TERM

Long term project closures listed below typically take place 24 hours a day, 7 days a week. Project completion dates typically range from 31 days up to a year, weather permitting.

 

JOHNSON COUNTY

K-7 at I-35 Pavement Replacement Project
Overall project work is scheduled to be completed by late September 2014

EXPECT DELAYS! UPCOMING FULL ROADWAY CLOSURE: Northbound and southbound K-7 will be CLOSED to through traffic between the northbound and southbound I-35 exit ramps for pavement replacement work beginning on Monday, April 28, sometime after morning rush hour, through mid-July 2014. A marked detour will be provided. Traffic will detour via the interchange ramps. Access will be maintained to local businesses throughout the project duration. This portion of the project work is scheduled to be completed in mid-July 2014. (New 4-23-14)

LEAVENWORTH COUNTY

No project closures at this time.

WYANDOTTE COUNTY

I-70 Tower Lighting Replacement Project (38th Street to 10th Street)
Overall project work is scheduled to be completed by late May 2014

RANDOM NON-PEAK LANE/SHOULDER CLOSURES: Eastbound and westbound I-70 from 38th Street to 10th Street may have random non-peak lane and shoulder closures for tower lighting replacement work beginning on Monday, March 10 through late May. Project work is scheduled to be completed in late May 2014. (New 3-12-14)

118th Street Over I-70 Bridge Replacement Project
Overall project work is scheduled to be completed in mid-November 2014

24/7 BRIDGE CLOSURE: 118th Street from Riverview Avenue to Speedway Boulevard will be CLOSED to all traffic for bridge replacement work beginning on Monday, March 17, 24/7 round the clock, throughout the project duration. A marked detour will be provided via 110th Street. Access to Sunflower Hills Golf Course will remain open during the project duration. For golf course access, drivers will continue on Riverview Avenue to Tom Lally Drive. Project work is scheduled to be completed in mid-November 2014. (New 3-21-14)

Riverview Avenue at I-70 Bridge Replacement Project
The scheduled completion date for the entire project is Spring 2014

24/7 BRIDGE CLOSURE: Riverview Avenue Bridge over I-70 will be closed for bridge replacement work, 24/7 round the clock, beginning on Monday, March 18. Riverview Avenue will be closed between 126th Street and 118th Street, and 122nd Street will be closed at Kansas Avenue. These closures will remain in effect until the new alignments of Riverview Avenue and 122nd Street are completed which is scheduled for early June 2013, weather permitting. At that time, Riverview Avenue will reopen from 118th Street to 122nd Street, but will remain closed from 122nd Street to 126th Street for the duration of the project. A marked detour will be provided.

 

 

 

 

Links of Interest

TopekaMetroKDOT on Twitter

Amelia Earhart Memorial Bridge Project

Lewis & Clark viaduct concept study

Subscribe to Kansas City Metro Traffic and News Information

TopekaMetroKDOT on Twitter

NEKansasKDOT on Twitter

KansasCityKDOT on Twitter