Daily Traffic Information

 

for

 

Tuesday, September 1, 2015


 

(NEW - REVISED)

 


 

SHORT TERM

 

Short term project closures listed below typically take place during daylight hours. Project completion dates typically range from 1 to 30 days. All closures and scheduled work are weather permitting and subject to change.

 

 

JOHNSON COUNTY 

   >  >  #Jocogateway

K-10 & I-435 to Renner Boulevard to Ridgeview Road Interchange

EXPECT DELAYS! WEEKDAY LANE CLOSURE: Eastbound K-10 LEFT LANE from Renner Boulevard to Ridgeview Road and westbound K-10 RIGHT LANE at I-435 (with right shift before Renner Boulevard to Ridgeview Road) will be CLOSED for trucks entering/leaving project work zone and bridge work/grading on Tuesday, September 1 between 9 a.m. and 3 p.m. Project work is scheduled to be completed on Tuesday, September 1. (NEW 8-31-15)

EXPECT DELAYS! WEEKDAY LANE CLOSURE: Northbound I-435 RIGHT LANE at K-10 will be CLOSED for concrete work on Tuesday, September 1 between 9 a.m. and 3 p.m. Project work is scheduled to be completed on Tuesday, September 1. (NEW 8-28-15)

EXPECT DELAYS! UPCOMING WEEKDAY LANE CLOSURE: Eastbound K-10 LEFT LANE and westbound K-10 RIGHT LANE from Renner Boulevard to Ridgeview Road will be CLOSED for trucks entering/leaving project work zone on Wednesday-Thursday, September 2-3 between 9 a.m. and 3 p.m. Project work is scheduled to be completed on Thursday, September 3. (NEW 8-31-15)

K-10 & Renner Boulevard Interchange

EXPECT DELAYS! FULL LONG-TERM INTERCHANGE CLOSURE: All lanes of Renner Boulevard north of the westbound K-10 rampsthe westbound K-10 to Renner Boulevard exit ramp and the Renner Boulevard to westbound K-10 entrance ramp will be CLOSED to all traffic, 24/7 round the clock, beginning at 1 a.m. this Thursday, July 23 through Friday, September 11, weather permitting. These closures are needed as crews complete reconstruction work on the interchange ramps and on Renner Boulevard both north and south of K-10. Marked detours will be provided. SPECIAL NOTE: Eastbound and westbound K-10 over the Renner Boulevard bridges will remain open to all traffic during this time, though there will be varying daily lane closures on K-10 in this area. Project work is scheduled to be completed on Friday, September 11. (REV. 8-31-15)

Westbound K-10 Split Lane at Renner Boulevard 

NEW SPLIT LANE TRAFFIC SHIFT: Westbound K-10 LEFT LANE at Renner Boulevard has been shifted to the south onto existing eastbound K-10 mainline pavement as of late Saturday, July 25, so that crews can complete reconstruction work in the K-10 and Renner Boulevard Interchange area. Westbound K-10 split lane traffic is separated by concrete barrier from the eastbound K-10 traffic in this side-by-side traffic shift. This dedicated westbound K-10 split lane is scheduled to be shifted back to its normal alignment by early September 2015, weather permitting. Project work is scheduled to be completed by early September. (NEW 7-30-15)

Lenexa Drive

EXPECT DELAYS! SHORT-TERM ROADWAY CLOSURE: Southbound Lenexa Drive from 99th Street to Pflumm Road will be CLOSED for storm sewer and curb work beginning at 5 a.m. on Wednesday, August 26 through Monday, September 7. Marked detour will be provided via 99th Street to Rosehill Road to 103rd Street to Pflumm Road. Project work is scheduled to be completed on Monday, September 7. (NEW 8-19-15)

EXPECT DELAYS! UPCOMING WEEKDAY OVERNIGHT FULL ROADWAY CLOSURES: Northbound and southbound Lenexa Drive from Pflumm Road to 99th Street will be CLOSED overnight for asphalt work beginning at 10 p.m. on Monday-Wednesday, September 7-9 and will reopen to all traffic at 5 a.m. on Tuesday-Thursday, September 8-10, weather permitting. A marked detour will be provided. Lenexa Drive traffic will detour via Rosehill Road and 103rd Street. Project work is scheduled to be completed on Thursday, September 10. (NEW 8-28-15)

EXPECT DELAYS! UPCOMING 24/7 LONG-TERM FULL ROADWAY CLOSURE: Northbound and southbound Lenexa Drive at Pflumm Road intersection and northbound and southbound Pflumm Road (under I-35 bridges) will be CLOSED, 24/7 round the clock, for roadway reconstruction work beginning on Thursday, September 10 and will reopen to all traffic on Saturday, October 24, weather permitting. A marked detour will be provided. Lenexa Drive traffic will detour via 103rd Street to Quivira Road to 95th Street. Project work is scheduled to be completed on Saturday, October 24. (NEW 8-28-15)

Santa Fe Drive

EXPECT DELAYS! OVERNIGHT FULL ROADWAY CLOSURE: Santa Fe Trail Drive from 101st Terrace to 105th Street will be FULLY CLOSED overnight for overhead I-435 bridge demolition work beginning at 7 p.m. (originally scheduled for 10 p.m.) on Monday, August 31 and will reopen to all traffic at 5 a.m. on Tuesday, September 1, weather permitting. Advance message boards will alert drivers to the full roadway closure. A marked detour will be provided. Santa Fe Trail Drive traffic will detour via 101st Terrace to Lackman Road to 105th Street. Project work is scheduled to be completed on Tuesday, September 1. (NEW 8-28-15)


I-35

EXPECT DELAYS! WEEKDAY LANE CLOSURES: Northbound and southbound I-35 LEFT LANES 75th Street to 7th Street will be CLOSED one direction at a time for brooming of the barrier wall via a moving operation on Tuesday, September 1. Project work is scheduled to be completed on Tuesday, September 1. (NEW 8-31-15)

U.S. 69 from 119th Street to I-435 & at 167th Street Interchange

EXPECT DELAYS! UPCOMING WEEKDAY OVERNIGHT LANE CLOSURES: Northbound and southbound U.S. 69 at 167th Street and from 119th Street to I-435 will be reduced to ONE OPEN LANE each direction for bridge repair work beginning at 7 p.m. on Thursday-Monday, September 10-14 and reopening to all traffic at 5 a.m. on Friday-Tuesday, September 11-15. Project work is scheduled to be completed on Tuesday, September 15. (NEW 8-31-15)

 

 

LEAVENWORTH COUNTY

 

K-7 from Pine Street to Limit Street

EXPECT DELAYS! WEEKDAY LANE CLOSURE: Southbound K-7 from Pine Street to Limit Street (Leavenworth) will be reduced to ONE OPEN LANE for City of Leavenworth ADA sidewalk project work beginning on Monday, June 29 daily, Monday-Friday, between 7 a.m. and 5 p.m. Expect some occasional Saturday work as needed. Work will first take place on the southbound side of K-7 and then will move to the northbound side of K-7. Project work is scheduled to be completed in early September 2015. (NEW 6-29-15)

U.S. 73/K-7 Reconstruction Project Update (From 20th Street to 4th Street)

EXPECT DELAYS! 24/7 LANE CLOSURES: Phase Seven work (from eastbound/southbound 12th Street to 10th Street) officially began ahead of schedule TODAY, Monday, August 31, which means that eastbound/southbound U.S. 73/K-7 from 16th Street to 10th Street is now reduced to ONE OPEN LANE each direction with no access from the side roads in this area. 

Phase Eight work (from eastbound/southbound 10th Street to 7th Street) is tentatively scheduled to begin on Monday, September 14, weather permitting.

Phase Five work (westbound/northbound U.S. 73/K-7 (16th Street to 20th Street) is scheduled to be completed in mid-September 2015, weather permitting.

Phase Six work (eastbound/southbound U.S. 73/K-7 from 16th Street to 12th Street) is scheduled to be completed in early October 2015, weather permitting.

Phase Seven work (eastbound/southbound U.S. 73/K-7 from 12th Street to 10th Street) is scheduled to be completed in mid-October 2015, weather permitting.

Phase Eight work (eastbound/southbound U.S. 73/K-7 from 10th Street to 7th Street) is scheduled to be completed in mid- to late October 2015, weather permitting.

Phased project work will move west in the north side lanes of U.S. 73/K-7 to the 20th Street interchange and then work will switch to the south side lanes of U.S. 73/K-7 as crews head back east to 7th Street. U.S. 73/K-7 traffic will be placed side by side and reduced to one lane each direction, 24/7 round the clock, through each construction phase throughout the project duration. The U.S. 73/K-7 Pavement Replacement Construction Project Handout is available online: http://www.ksdot.org/Assets/wwwksdotorg/bureaus/kcMetro/pdf2015/U.S.%2073%20-%20K-7%20Pavement%20Replacement%20Construction%20Project%20Handout%20-%20Leavenworth%20County.pdf. Overall project work is scheduled to be completed in mid-December 2015. (REV. 8-31-15)

 

 

WYANDOTTE COUNTY

 

I-70 & I-635 Interchange

EXPECT DELAYS! UPCOMING WEEKDAY RAMP CLOSURES: Westbound I-70 to southbound I-635 ramp will be CLOSED for bridge inspection work via snooper truck on Wednesday-Thursday, September 2-3 between 9 a.m. and 4 p.m. Project work is scheduled to be completed on Thursday, September 3. (NEW 8-28-15)

I-70 Multi-Bridge Repair Project

Park Drive

WEEKDAY LANE CLOSURES: Northbound and southbound Park Drive at I-70 will have varying lane closures for bridge painting work on Monday-Wednesday, August 31-September 1-2 between 7 a.m. and 5:30 p.m. Project work is scheduled to be completed on Wednesday, September 2. (NEW 8-27-15)

I-435 & Parallel Parkway Interchange 

EXPECT DELAYS! 30-DAY 24/7 LANE & RAMP CLOSURE: Northbound I-435 to eastbound Parallel Parkway exit ramp and the eastbound Parallel Parkway RIGHT LANE under the I-435 bridges will be CLOSED for pavement reconstruction work, 24/7 for 30 days, beginning at 9 a.m. on Monday, August 17 and reopening to all traffic in mid-September 2015, weather permitting. These closures are needed to allow the project contractor, Clarkson Construction, to build a turn lane at the bottom of the ramp that will serve the new auto mall located on the southeast corner of the interchange. Advance message boards will alert drivers to the lane and ramp closures. A marked detour will be provided for the ramp closure. Northbound I-435 to eastbound Parallel Parkway ramp traffic will detour on northbound I-435 to eastbound K-5/Leavenworth Road to southbound 99th Street to access eastbound Parallel Parkway. Project work is scheduled to be completed in mid-September 2015. (NEW 8-4-15)

U.S. 69/18th Street Expressway from Wyandotte/Johnson County Line to K-32

EXPECT DELAYS! WEEKDAY LANE CLOSURES: Northbound US-69/18th Street Expressway from I-35 to Merriam Drive will be reduced to ONE OPEN LANE for pavement repair work on Monday-Tuesday, August 31-September 1 between 9 a.m. and 3:30 p.m.  Project work is scheduled to be completed on Tuesday, September 1. (NEW 8-28-15)

EXPECT DELAYS! WEEKDAY LANE CLOSURES: Northbound US-69/18th Street Expressway from Merriam Drive to K-32 will be reduced to ONE OPEN LANE for pavement repair work on Monday-Tuesday, August 31-September 1 between 9 a.m. and 8 p.m.  Project work is scheduled to be completed on Tuesday, September 1. (NEW 8-28-15) 

EXPECT DELAYS! WEEKDAY LANE CLOSURES: Northbound and southbound U.S. 69/18th Street Expressway from Wyandotte/Johnson County Line to K-32 will be reduced to ONE OPEN LANE for both directions, in sections at a time, as crews begin pavement repair work at 9 a.m. on Monday, August 31 through mid-September, weather permitting. Work will also take place on the ramps at Merriam Lane, Steele Road, Ruby Street, Kansas Avenue and I-35. Work will take place during daylight hours, Monday through Saturday. No work will be allowed south of Merriam Lane between 6-9 a.m. and 3-7 p.m. on mainline lanes, and between 9-8:30 a.m. and 3:30-6:30 p.m. on adjacent ramps. Project work is scheduled to be completed in Mid-September 2015. (NEW 8-28-15)

 

 


  

LONG TERM

  

Long term project closures listed below typically take place 24 hours a day, 7 days a week. Project completion dates typically range from 31 days up to a year. All closures and scheduled work are weather permitting and subject to change.

 

JOHNSON COUNTY

 

 > > #Jocogateway 

Northbound I-35 Dedicated Through Lane

24/7 DEDICATED THROUGH LANE ADDITION: Northbound I-35 FAR LEFT LANE from I-435 to 95th Street will be shifted to the existing southbound I-35 far left lane (and placed between concrete barriers) to create a “dedicated through lane” beginning early morning on Sunday, April 26, weather permitting, so crews can complete widening work on northbound I-35 and on the Pflumm Road bridge. This lane is similar to the westbound I-435 left through lane that was created for ongoing construction work. This northbound I-35 dedicated through lane is scheduled to be removed from use in November 2015. (REV. 7-9-15)

K-10 & Renner Boulevard Interchange Project

EXPECT DELAYS! FULL LONG-TERM INTERCHANGE CLOSURE: All lanes of Renner Boulevard north of the westbound K-10 rampsthe westbound K-10 to Renner Boulevard exit ramp and the Renner Boulevard to westbound K-10 entrance ramp will be CLOSED to all traffic, 24/7 round the clock, beginning at 1 a.m. this Thursday, July 23 through Friday, September 11, weather permitting. These closures are needed as crews complete reconstruction work on the interchange ramps and on Renner Boulevard both north and south of K-10. Marked detours will be provided. SPECIAL NOTE: Eastbound and westbound K-10 over the Renner Boulevard bridges will remain open to all traffic during this time, though there will be varying daily lane closures on K-10 in this area. Project work is scheduled to be completed on Friday, September 11. (REV. 8-31-15)

Lackman Road to Eastbound I-435 Ramp  

EXPECT DELAYS! 24/7 LONG-TERM RAMP CLOSURE: Lackman Road to eastbound I-435 entrance ramp will be CLOSED, 24/7 round the clock, for full ramp reconstruction work beginning at 10 p.m. on Friday, August 14 and will reopen to all traffic on Monday, November 2, weather permitting. Advance message boards will alert drivers to the ramp closure. A marked detour will be provided. Southbound Lackman Road ramp traffic will detour via westbound College Boulevard to northbound Renner Boulevard to the new Renner Boulevard to eastbound K-10 ramp to access eastbound I-435. An optional recommended detour route for southbound Lackman Road traffic is eastbound College Boulevard to Quivira Road to access eastbound I-435. Northbound Lackman Road ramp traffic will detour via westbound 95th Street to access the I-435 ramps. Project work is scheduled to be completed on Monday, November 2. (REV. 8-13-15) 

Pflumm Road Under I-35 Bridges

24/7 FULL ROADWAY CLOSURE: Northbound and southbound Pflumm Road under the I-35 bridges between Lenexa Drive (on the south) and Marshall Drive (on the north) will be FULLY CLOSED to all traffic, 24/7 round the clock, for I-35 roadway reconstruction and bridge widening beginning at 7:00 a.m. on Wednesday, May 27 through early October 2015,weather permitting. Project work is scheduled to be completed in October 2015. (REV. 5-22-15)


I-35 from 151st Street to Santa Fe/135th Street Pavement Reconstruction Project
Overall project work is scheduled to be completed in September 2016

PROJECT TO BE SUSPENDED FOR 2015-2016 WINTER SEASON: Due to weather-related delays, KDOT and Ideker, Inc. are currently working on a revised schedule that will delay the start of Phase Two construction into next year (Spring 2016). Reconstructing both lane directions of I-35 through the project area in one construction season, although very aggressive, was a reasonable expectation and was intended to minimize the impact to the traveling public. Unfortunately, the unprecedented amount of rainfall events that have occurred throughout this construction season have delayed the construction work beyond what could be reasonably anticipated. Because the work is very structured, it limits the contractor’s ability to adjust their scope of work and make up for these delays. The decision to break between phases and go into a second construction season was based on the risks associated with replacing the pavement on the northbound I-35 lanes during the Kansas winter months.

Here’s what this means for drivers > > We are tentatively expecting Phase One construction to be completed by early September 2015 (around Labor Day), at which time traffic will be switched back to its original configuration until work begins again next spring (March-April 2016). This means that northbound I-35 will be shifted back to the existing northbound lanes and southbound I-35 will travel on the newly reconstructed lanes. The Santa Fe Street/135th Street to southbound I-35 entrance ramp and the southbound I-35 to Old U.S. 56 exit ramp will be reopened to all traffic at this time. Advance separate notification will be sent out as the early September phase one completion date nears to alert drivers to the traffic switch back to the normal configuration and the reopening of the ramps to all traffic.           

REMINDER: During Phase Two construction, the Santa Fe Street/135th Street to southbound I-35 entrance ramp, the Old U.S. 56 to northbound I-35 entrance ramp, and the northbound I-35 to Santa Fe Street/135th Street exit ramps will be closed. Advance separate notification will be sent out early next year (2016) alerting drivers as to when construction is set to begin again on the project.  Though the project completion date will be extended from the original date of November 2015 to September 2016, weather permitting, it should be noted that the time of traffic impacts will increase by approximately three months overall when compared to the original schedule. Overall project work is scheduled to be completed in September 2016. (NEW 8-5-15)

EXPECT DELAYS! 24/7 RAMP CLOSURES:  Northbound and southbound I-35 from just north of 151st Street to just north of Santa Fe Street/135th Street will have varying lane and ramp closures for reconstruction work beginning on Monday, March 16. Construction will be completed in two phases. Each phase will take approximately four months to complete, weather permitting. During the weeks of March 16-30, crews will begin project work by setting traffic control followed by construction of median crossovers located at either end of the project. Traffic impacts include lane reductions on I-35 and the closure of the Santa Fe Street/135th Street to southbound I-35 entrance ramp throughout the project duration. Ramp closures and lane reductions are tentatively scheduled to begin sometime around Monday, March 30, weather permitting. Phase One. All I-35 traffic will be carried on the existing northbound lanes separated by concrete barrier while the southbound lanes are reconstructed. During this phase, the southbound I-35 to Old U.S. 56 exit ramp will be closed. Southbound I-35 to Old U.S. 56 ramp traffic will detour via the U.S. 169/K-7 exit then north on K-7 to Old U.S. 56. Approximate timeframe for completion work on this phase: April-August 2015, weather permitting. Phase Two. All I-35 traffic will be carried on the newly completed southbound lanes separated by concrete barrier while the northbound lanes are reconstructed. During this phase, the Old U.S. 56 to northbound I-35 entrance ramp and the northbound I-35 to Santa Fe Street/135th Street exit ramp will be closed. Approximate timeframe for completion work on this phase: August-December 2015, weather permitting. Santa Fe Street/135th Street to southbound I-35 ramp traffic will detour via Mur-Len Road south to 151st Street west to I-35 or via Ridgeview Road north to 119th Street east to I-35.  Project work is scheduled to be completed in September 2015. (REV. 8-3-15)

The I-35 Pavement Replacement Project in Johnson County Public Handout is available online: http://www.ksdot.org/Assets/wwwksdotorg/bureaus/kcMetro/pdf2015/I-35%20Pavement%20Replacement%20Project%20in%20Johnson%20County%20Handout%2035-46%20KA-3560-01.pdf. This handout includes detailed information for construction phasing, traffic impacts and detour routes for the pavement replacement project taking place on a two-mile stretch of northbound and southbound I-35 from just north of 151st Street to just north of Santa Fe Street/135th Street in Olathe (Johnson County).        

U.S. 69 & 159th Street Interchange Project

EXPECT DELAYS! 24/7 LANE CLOSURES: Northbound and southbound U.S. 69 from 151st Street to 167th Street will be REDUCED TO ONE OPEN LANE each direction, 24/7 round the clock, for City of Overland Park 159th Street interchange project work beginning on Tuesday, June 23 through Monday, September 7, 2015. Project work is scheduled to be completed on Monday, September 7. (NEW 6-24-15)   

WEEKDAY LANE/SHOULDER CLOSURES: Northbound and southbound U.S. 69 from 151st Street to 169th Street may have periodic lane and shoulder closures for ramp construction work beginning in September 2014 through late October 2015. KDOT partnered on a city-led project with the City of Overland Park for the U.S. 69 & 159th Street interchange expansion project. This expansion project includes the addition of interchange ramps to the existing intersection at U.S. 69 and 159th Street in Overland Park (Johnson County). The project work zone on northbound and southbound U.S. 69 will extend from 151st Street south to 169th Street throughout the duration of the project. Construction work, including periodic lane and shoulder closures, will primarily occur during daylight hours Monday through Friday. Project work is scheduled to be completed in late October 2015. (NEW 12-15-14)

 

 

LEAVENWORTH COUNTY

 

U.S. 73/K-7 Reconstruction Project Update (From 20th Street to 4th Street)

EXPECT DELAYS! 24/7 LANE CLOSURES: U.S. 73/K-7 from 16th Street to 20th Street is reduced to ONE OPEN LANE lane each direction, 24/7 round the clock, as Phase Five pavement reconstruction work began on Monday morning, August 10. Phase Four work (from 12th Street to 16th Street) began on July 6 and was completed and reopened to all traffic on Friday, August 7. Phase Five work is scheduled to be completed in mid-September 2015, weather permitting.  The U.S. 73/K-7 Pavement Replacement Construction Project Handout is available online: http://www.ksdot.org/Assets/wwwksdotorg/bureaus/kcMetro/pdf2015/U.S.%2073%20-%20K-7%20Pavement%20Replacement%20Construction%20Project%20Handout%20-%20Leavenworth%20County.pdf. Overall project work is scheduled to be completed in mid-December 2015. (REV. 8-14-15)

Missouri Route: I-29  > > KCI Airport Travel Impacts

EXPECT DELAYS! 24/7 LANE & RAMP CLOSURES: Motorists should prepare for delays as MoDOT crews work to rehabilitate 12 bridges along the I-29 corridor between I-435 and I-635 in Platte County, MO beginning on Tuesday, April 21 and continuing for six months. Work will cause lane reductions, narrow lanes, and ramp closures. Motorists should use alternate routes such as I-435 and U.S. 169. The following impacts will be underway: 

  • Two lanes of I-29 will be maintained in each direction between 112th Street and Route 45 (64th Street).
  • I-29 will be reduced to one lane at Route D (Cookingham Drive) for each direction for 80 calendar days.
  • The ramp from eastbound Route 152 to southbound I-29 will be closed for the duration of the project.
  • I-29 lanes will be narrowed at the bridge locations.

Temporary lane closures may be encountered on Route D (Cookingham Drive), 112th Street, Tiffany Springs Parkway, Barry Road, 72nd Street, and Route 45 (64th Street) during off peak hours. Project work is scheduled to be completed in Fall 2015. (REV. 4-20-15)

 

WYANDOTTE COUNTY

 

I-70 Multi-Bridge Repair Project

EXPECT DELAYS! 24/7 LANE CLOSURES: Eastbound I-70 from just west of I-635 to just east of Kaw Drive and all westbound I-70 traffic will be shifted from the left two lanes to one mainline right lane on I-70 and the other westbound I-70 lane will run along the collector-distributor road just past 18th Street Expressway to I-635. Eastbound and westbound I-70 traffic will remain in the two through lanes as mentioned above for the duration of the project. 

Project construction information, including general phasing, traffic impacts and marked detour route maps can be viewed at: I-70 over Kaw Drive Multi-Bridge Construction Project Handout.  The overall project work is scheduled to be completed in late December 2015. (REV. 8-21-15)

I-435 Missouri River Bridge Repair Project

24/7 LANE CLOSURE: Northbound and southbound I-435 over the Missouri River Bridge (including .05-miles on either side of the bridge) will be reduced to two open lanes for bridge repair work, 24/7 round the clock, beginning at 7:00 a.m. on Thursday morning, April 30, throughout the project duration. The overall project work is scheduled to be completed in December 2015. (NEW 4-28-15)

U.S. 69 over Missouri River Bridge Replacement Project (MoDOT/KDOT Project) > #us69moriverbridge

24/7 LANE CLOSURES: Northbound and southbound U.S. 69 from I-635 (in Missouri) to Kindleberger Road in Kansas will be reduced to one lane in each direction, 24/7, beginning on Friday, October 24 for bridge replacement work. Both northbound and southbound U.S. 69 traffic will travel on the existing northbound U.S. 69 bridge (Platte Purchase Bridge). A crossover will be used to shift southbound U.S. 69 traffic to the existing Platte Purchase Bridge. The traffic switch is scheduled for Friday, October 31, 2014 and traffic will remain in this configuration until Thursday, December 1, 2016. Project work is scheduled to be completed on Thursday, December 1, 2016. (NEW 10-27-14)

K-5

EXPECT MINOR DELAYS! 24/7 LANE CLOSURE: Southbound K-5 RIGHT LANE from approximately I-635 to 18th Street was CLOSED to all traffic beginning at 2:30 p.m. TODAY, Thursday, June 18 and will remain closed, 24/7 round the clock, until emergency pavement repair work can be completed for a small sinkhole that has appeared. Repair work should be completed sometime in early July 2015, weather permitting. All adjacent ramps will remain open to traffic. Project work is scheduled to be completed in late September 2015. (REV. 8-31-15)